Using the project management case study, Calculate the Net Present Value (NPV) for the project business case. (Use Microsoft Excel to derive the NPV assuming the data below—submit an Excel spreadsheet...

1 answer below »
Using the project management case study,
  • Calculate the Net Present Value (NPV) for the project business case. (Use Microsoft Excel to derive the NPV assuming the data below—submit an Excel spreadsheet as an appendix:
    • Purchase price of $400,000.
    • One-time project costs total of $100,000 spent in Year 0.
    • Net benefits after taxes of $150,000 per year for five years.
    • Salvage value for Year 6 and beyond of $400,000.)
  • Summarize your results of NPV in the paper and refer to the Appendix.
Answered Same Day Sep 25, 2021

Solution

Ashish answered on Sep 26 2021
154 Votes
Sheet1
    Solution-
        Assume Rate of Interest:
        Interest Rate    8%    10%
        Year    Cash Inflows    Cash Inflows
        0    ($500,000)    ($500,000)
        1    $150,000    $150,000
        2    $150,000    $150,000
        3    $150,000    $150,000
        4    $150,000    $150,000
        5    $150,000    $150,000
        Salvage...