PM Task - Part XXXXXXXXXX ENGG6830 - Project Management Assignment Project Management Task – Tools Part 1 - Plan Due by Friday April 5th 2019 This is an individual assessment. Installing an Assembly...

1 answer below »
PM Task - Part XXXXXXXXXX
ENGG6830 - Project Management Assignment
Project Management Task – Tools
Part 1 - Plan

Due by Friday April 5th 2019
This is an individual assessment.

Installing an Assembly Line of Packaging Machines

This assessment has been developed to provide enough information to enable development of a project
plan. In the planning stage, you are required to determine tasks, some durations, predecessors and
allocate resources.

The Scenario:

You have been asked to plan a project for the internal installation and implementation of an assembly
line of X new plastic injection machines ($80,000= each) and Y new drilling machines ($8,500= each)
using the company existing personnel. The requirements are:

s Ordering the machines
s Unpack the imported pre-ready machines for installation
s Lay the machine foundations
s Lay electrical cabling
s Installation
s Connect the machine to power supply
s Commissioning

NOTE:
X and Y co
espond to your student number’s last digit and your student number’s second last digit
espectively. In the case that any of the digits is zero, just take the digit that is not zero as the value for
X or Y. If both digits are zero, then take 7 as the value for each X and Y.

The project is planned to start on, Monday, June 3rd XXXXXXXXXXTHE EXPECTED DURATION OF THE
PROJECT IS NO LONGER THAN 85 DAYS.

The schedule will be based on a standard 40-hour working week, and consider that the following day is
a holiday: Monday June 10th.


Your project planning should allow for:

s Management’s Approval of project (allow 3 days, 3 hours cost) - Manager
s Machines have to be ordered (1 day, 6= hours cost) – Technical manager.
s Management’s Approval of installation project once the machines have a
ived (allow 5
days, 2 hours cost) - Manager.
s Order necessary equipment, Electrical cables, cement, etc. costing $9,700= (1 day, 4 hours
cost) – Technical manager.
s Machines and necessary equipment a
ival will take 3 weeks – 21 days.
s Allow 7 days for foundations to harden – Technical Assistants and fitter take 1 day doing
this.
s Allow 3 days for cabling work for all machines - Electrician.
s Allow ½ a day unpacking per machine – Technical Assistant.
s An injection machine is estimated to take 2 days to be installed by two people – A
Technical Assistant and a Fitter
s A drilling machine is estimated to take 4 days to be installed by two people – A Technical
Assistant and a Fitter.
s Testing each injection machine is estimated to take 4 hours (½ a day) each – One Technical
Assistant.
s Testing each drilling machine is estimated to take 6 hours each - One Technical Assistant.

Note: You might notice that some tasks have duration and cost that are not equal, e.g. allow 4 days and
7 hours cost. Both are used as they are, duration will affect the Gantt chart and activity network,
ut the cost is effective working time associated to the task and therefore its cost.

The company's resources are as follows:
K. Tan - Manager $80/hr
J. Wilson - Technical Manager $60/hr
T. Gunther - Chief Accountant $45/hr
T. McMaster - Electrician $35/hr
B. Farmer - Fitter $30/hr
B. Picossi - Technical Assistant #1 $25/hr
B. Barnes - Technical Assistant #2 $25/hr

You need to take the following into account:

s Electricians can only work on the installation during weekends, so as to not inte
upt power
supply (rate of labour per hour on weekends is 1.25).
s Two people are required to install a machine (a fitter and a technical assistant).
s Testing can be done once installed and during weekdays.
You are required to submit:
s A WBS for the project including personnel costs. It could be one of:
o If you manage the project using any project management software like ProjectLi
e,
the one it supplies can be submitted,
o A graphic done in any graphical software adding the personnel cost.
s A Dependency Matrix of the project as per lecture slides.
s AOA Network identifying times and Critical Path as per lecture slides.
s A Gantt Chart of the plan. It could be one of:
o If you manage the project using any project management software like ProjectLi
e,
the one it supplies can be submitted, or
o A Gantt charts produced in MS Excel.

Marking Schema for PM Task (Part 1 and Part 2):

Objectives Total Points
Presentation & Assumptions 5
Dependency Matrix 8
WBS 7
AOA 20
GANTT Chart 30
S-Curve 15
EVM 15

PLEASE NOTE:

A) The above is all of the information that you will be provided with concerning this PART1
task.
B) The information is not necessarily complete and may therefore require you to make
assumptions, if you do, then STATE THEM CLEARLY AND SUPPORT THEM.
C) Please prepare your submission in the same way that you would like to receive it if you were a
manager. You must submit a report as if it was to be given to your supervisor in a company.
D) ProjectLi
e is a free resource available for you to download.

About the submission:
In order to submit, we will be using Blackboard/Turnitin. Therefore, there will be two
submission links:
a) Coversheet submission link: submit only your cover sheet. Assignment Cover Sheets
(ACSs) is available electronically (Blackboard). A completed and signed paper ACS
must accompany all assignment submissions.
) PM Task – Part 1: Plan submission link: submit only your report in word or pdf
document (Gantt charts, tables, graphs must be included in the report).

Any assessment items received after the due date will attract a penalty of 10% of available
marks for each calendar day overdue. A block extension to a due date will only be granted in
exceptional circumstances (see policy - SPECIAL CIRCUMSTANCES AFFECTING
ASSESSMENT ITEMS).
The marks will be available in Blackboard. Any question about the marking, write/talk to your
course coordinator.

C. Sanin -2019
Answered Same Day Mar 21, 2021

Solution

Amar answered on Mar 29 2021
158 Votes
1
Running Header: ENGG6830 - Project Management Assignment - Part 1: Plan
2
ENGG6830 - Project Management Assignment - Part 1: Plan
ENGG6830 - Project Management Assignment - Part 1: Plan
    ENGG6830 - Project Management Assignment - Part 1: Plan    
Work Breakdown Structure (“WBS”)
The WBS in the form of work tasks
oken down to three levels, dependencies, schedule, and cost are presented in the following tables (Kerzner & Kerzner, 2017; Kerzner, 2018; Turner, 2016) –
Table 1 – WBS (Work Tasks)
    WBS ID
    LEVEL 0
    LEVEL 1
    LEVEL 2
    1
    Installing an Assembly Line of Packaging Machines
     
     
    1.1
     
    Project Planning Work Package
     
    1.1.1
     
     
    Project Initiation
    1.1.2
     
     
    Charter Approval
    1.1.3
     
     
    Team Hiring
    1.1.4
     
     
    Project Processes Planning
    1.1.5
     
     
    Project Management Plan Documentation
    1.1.6
     
     
    Work Package Closure
    1.2
     
    Requirements Analysis
     
    1.2.1
     
     
    Data Collection
    1.2.2
     
     
    Requirements Review
    1.2.3
     
     
    Team discussions
    1.2.4
     
     
    Requirements Assessments
    1.2.5
     
     
    Requirements Identification
    1.3
     
    Procurements
     
    1.3.1
     
     
    Ordering of all the Machines
    1.3.2
     
     
    Approval from the Management for Installing the project After A
ival of the Machines
    1.3.3
     
     
    Ordering All Necessary Equipment, Electrical cables, Cement, and others
    1.3.4
     
     
    Machines & Necessary Equipment A
iving
    1.3.5
     
     
    Work Package Closure
    1.4
     
    Implementation & Installation
     
    1.4.1
     
     
    Foundations Left for Hardening
    1.4.2
     
     
    Cabling Works for all of the 6 Machines
    1.4.3
     
     
    Unpacking All of the Machines
    1.4.4
     
     
    Injection Machines to be Installed
    1.4.5
     
     
    Drilling Machines to be Installed
    1.4.6
     
     
    Testing Each of the Injection Machines
    1.4.7
     
     
    Testing Each of the Drilling Machines
    1.5
     
    Project Close-out
     
    1.5.1
     
     
    Success Evaluation
    1.5.2
     
     
    Outcome Review
    1.5.3
     
     
    Learnings Documentation
    1.5.4
     
     
    Sign-of
Table 2 – Detailed Work Breakdown with Schedule
    REF#
    TASKS
    Duration
    Start Date
    End Date
    Predecesso
    1
    Installing an Assembly Line of Packaging Machines
    76 days
    01/04/19 8:00
    15/07/19 17:00
     
    2
    Project Planning Work Package
    3 days
    01/04/19 8:00
    03/04/19 17:00
     
    3
    Project Initiation
    0.5 days
    01/04/19 8:00
    01/04/19 13:00
     
    4
    Charter Approval
    0.5 days
    01/04/19 13:00
    01/04/19 17:00
    3
    5
    Team Hiring
    0.5 days
    02/04/19 8:00
    02/04/19 13:00
    4
    6
    Project Processes Planning
    0.5 days
    02/04/19 13:00
    02/04/19 17:00
    5
    7
    Project Management Plan Documentation
    0.5 days
    03/04/19 8:00
    03/04/19 13:00
    6
    8
    Work Package Closure
    0.5 days
    03/04/19 13:00
    03/04/19 17:00
    7
    9
    Requirements Analysis
    5 days
    04/04/19 8:00
    10/04/19 17:00
     
    10
    Data Collection
    1 day
    04/04/19 8:00
    04/04/19 17:00
    8
    11
    Requirements Review
    1 day
    05/04/19 8:00
    05/04/19 17:00
    10
    12
    Team discussions
    1 day
    08/04/19 8:00
    08/04/19 17:00
    11
    13
    Requirements Assessments
    1 day
    09/04/19 8:00
    09/04/19 17:00
    12
    14
    Requirements Identification
    1 day
    10/04/19 8:00
    10/04/19 17:00
    13
    15
    Procurements
    29 days
    11/04/19 8:00
    21/05/19 17:00
     
    16
    Ordering of all the Machines
    1 day
    11/04/19 8:00
    11/04/19 17:00
    14
    17
    Approval from the Management for Installing the project After A
ival of the Machines
    5 days
    12/04/19 8:00
    18/04/19 17:00
    16
    18
    Ordering All Necessary Equipment, Electrical cables, Cement, and others
    1 day
    19/04/19 8:00
    19/04/19 17:00
    17
    19
    Machines & Necessary Equipment A
iving
    21 days
    22/04/19 8:00
    20/05/19 17:00
    18
    20
    Work Package Closure
    1 day
    21/05/19 8:00
    21/05/19 17:00
    19
    21
    Implementation & Installation
    25 days
    22/05/19 8:00
    25/06/19 17:00
     
    22
    Foundations Left for Hardening
    8 days
    22/05/19 8:00
    31/05/19 17:00
    20
    23
    Cabling Works for all of the 6 Machines
    3 days
    03/06/19 8:00
    05/06/19 17:00
    22
    24
    Unpacking All of the Machines
    3 days
    06/06/19 8:00
    10/06/19 17:00
    23
    25
    Injection Machines to be Installed
    2 days
    11/06/19 8:00
    12/06/19 17:00
    24
    26
    Drilling Machines to be Installed
    4 days
    13/06/19 8:00
    18/06/19 17:00
    25
    27
    Testing Each of the Injection Machines
    1 day
    19/06/19 8:00
    19/06/19 17:00
    26
    28
    Testing Each of the Drilling Machines
    4 days
    20/06/19 8:00
    25/06/19 17:00
    27
    29
    Project Close-out
    14 days
    26/06/19 8:00
    15/07/19 17:00
     
    30
    Success Evaluation
    5 days
    26/06/19 8:00
    02/07/19 17:00
    28
    31
    Outcome Review
    5 days
    03/07/19 8:00
    09/07/19 17:00
    30
    32
    Learnings Documentation
    3 days
    10/07/19 8:00
    12/07/19 17:00
    31
    33
    Sign-of
    1...