Unit 10 Individual Assignment Budget Estimating (100 points) This assignment consists of 2 parts: questions about budget estimation and developing a budget. Part 1 Questions (10 points) Provide...

1 answer below »
Unit 10 Individual Assignment

Budget Estimating (100 points)

This assignment consists of 2 parts: questions about budget estimation and developing a budget.

Part 1 Questions (10 points)

Provide responses to the following questions

1. You are providing a review of contractor bids for a component of your upcoming project. What can be done to determine whether or not a vendor’s bid is reasonable?

2. Describe the conditions for which parametric, analogous and bottom up estimation techniques work best, and provide 2 examples in support of each method.

3. Why is a cost management plan important? How does the plan benefit the project manager?

Part 1 responses should be presented in a question-response format. Use Arial font with 11 point. There is no word limit.

Part 2 Budget Estimating (30 points)

Using the same scenario from the previous unit on scheduling, create a time-phased budget for the following project. Prepare a figure like Exhibit 10.9 (see below), CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project.

Assume the following hourly rates:

Alcides $45 / hr.

Joan $50 / hr.

Activity ID

Activity

Immediate Predecessor

Duration in days

Resource

Work Hours per Day

A

Evaluate freezers

2

Alcides

6

B

Chart temperatures

6

Joan

4

C

Review service record

2

Alcides

D

Consult with HVAC engineer

A, B, C

3

Alcides

E

Develop construction plan

D

10

Joan

F

Complete IC assignment

E

2

Alcides

G

Complete ROI analysis

E

5

Joan

H

Conduct regulatory review

E

4

Joan

I

Obtain construction approval

F, G, H

2

Alcides

Part 3 Budget Estimating (50 points)

You are the project manager for a process improvement project for Company XYZ. Prepare a figure like Exhibit 10.9 (see below) that illustrates the weekly and cumulative costs for the resource-leveled project.

Hint: To accomplish this exercise, you’ll need to create a project schedule in MS Excel (or by hand), create resource assignments, assign costs to each resource, and assign the resources to each task. Some resource leveling will be required.

In this project, you have 3 employees: Ann, Becky and Clive. Each person is limited to the amount of time allocated to your project. Ann and Becky are available 30 hours/week; Clive is available 20 hours/week. There hourly rates are: Ann: $60/hour; Becky: $35/hour; and Clive: $50/hour.

WBS

Activity

Immediate Predecessor

Estimated Duration in weeks

Resource

1

Process Improvement Project

1.1

Operational definition

1.1.1

Research literature

3

Becky

1.1.2

Identify and define terms

1.1.1

1

Ann

1.1.3

Obtain approval of definition

1.1.2

2

Clive

1.2

Target Selection

1.2.1

Solicit partners for pilot

2

Ann

1.2.2

Hold brainstorming meeting

1.2.1

2

Becky

1.2.3

Identify characteristics of targets

1.2.2, 1.3.1

1

Ann

1.2.4

Obtain approval of partners

1.2.3, 1.1.2, 1.3.4

1

Clive

1.3

Question set

1.3.1

Identify process group members

2

Clive

1.3.2

Develop question set

1.2.3

4

Ann

1.3.3

Prototype and validate question set

1.3.2

3

Becky

1.3.4

Add partners

1.3.1, 1.2.1

3

Becky

1.4

Pilot process

1.4.1

Schedule with target audience

1.2.4

2

Becky

1.4.2

Conduct beta test

1.3.4, 1.2.4

2

Clive

1.4.3

Process feedback from target audience

1.4.2

2

Ann

1.4.4

Conduct pilot

1.4.3

2

Clive

1.4.5

Analyze results

1.4.4

2

Clive

Parts 2 and 3 Use MS Excel (MS Project is not acceptable) to create the budget estimate and present it similar to Exhibit 10.9. Show intermediate steps (schedule, resource schedule assignments, resource-leveled schedule and any other elements needed to create the time-phased budget estimate.

Answered 69 days After May 10, 2022

Solution

Tanmoy answered on Jul 18 2022
88 Votes
BUDGET ESTIMATING
Table of Contents
Part 1.    3
Part 2.    3
Part 3.    4
References    9
Part 1.
1) In order to understand if the bid of the contractor is fair or not, the bid must agree with the terms and conditions of the contract. Also, there must be a proper deadline as per the contract and thus it must adhere to the policies of fairness and transparency which are essential for the bid.
Also, when many vendors are competing for a project, it is the lowest bid which is considered as the best and the optimal deal. It is also the authenticity and reputation of the vendors which plays a crucial role. The bid must be at par with the project of the project estimates. The bid must comply with the terms and conditions of the project and must be formatted in a legal manner. Finally, it is essential to have impartiality and transparency for the bid.
2) Analogous view is dependent on the past results of the company along with the historical data. But, in this case both the historical and mathematical data are necessary for utilization in the parametric technique. Hence, it is bottom-up estimation which works on the WBS method helps in segregation of the complicated problem into minute units.
3) Cost management is a process of properly strategizing and administration of the organization’s budget. In terms of a project, it helps in assisting a project manager to estimate the cost of the project and implementing controls for lowering the chances of the project being over budgeted. The ultimate benefits of a project are that, it helps in offering valuable feedback and a direction to the project managers on efficiently managing the project costs in accordance with the budget (Sharma & Vaidya, 2022).
Part 2.
The project will take 26 days to get completed.
Part 3.
    WBS
    Activity
    Immediate Predecesso
    Estimated Duration in weeks
    Resource
    Start date
    1
    Â Process Improvement Project
    Â 
    Â 
    Â 
     3/23/2020
    1.1
    Â Operational definition
    Â 
    Â 
    Â 
    27-03-2020
    1.1.1
    Â Research literature
    Â 
    3
    Becky
    27-03-2020
    1.1.2
    Â Identify and define terms
    1.1.1
    1
    Ann
    01-04-2020
    1.1.3
    Â Obtain approval of definition
    1.1.2
    2
    Clive
     4/2/2020
    1.2
    Â Target Selection
    Â 
    Â 
    Â 
     3/23/2020
    1.2.1
    Â Solicit partners for pilot
    Â 
    2
    Ann
     3/23/2020
    1.2.2
    Â Hold
ainstorming meeting
    1.2.1
    2
    Becky
     4/1/2020
    1.2.3
    Â Identify characteristics of targets
    1.2.2, 1.3.1
    1
    Ann
    03-04-2020
    1.2.4
    Â Obtain approval of partners
    1.2.3, 1.1.2,...