1 answer below »
Kanban Project Plan Status Boards: (make sure to create these project plans based on AGILE/SCRUM Framework)
1.
1. Review Kanban Agile MethodologyLinks to an external site.
2. Review Kanban Project Status Board readings and ru
ic (see Ru
ic links): 
3. Deliverable: Create a Kanban Project Status Board in Microsoft Project
 or other method (using Excel, MS Word, or MS PowerPoint)  - name your files as; {StudentName_KanbanBoard]; [StudentName]_Original_KBProjectPlan); [StudentName]_Modified_KBProjectPlan)
4. If you choose to use MS Project, please follow this process.
· Review these instructions: Using Kanban Boards in Microsoft Project - MPUGLinks to an external site.
· Open MS Project
· Create New project plan (FILE/NEW)
· Select one of MS Project Plan or MS Excel templates that has 50+ tasks (including both summary tasks and sub tasks) (OR you can use any other project plan that you may have) (SAVE your project plan file as; [StudentName]_Original_KBProjectPlan)
· In this project plan, we want to update your project to indicate a cu
ent date (even in the future) and show BACKLOG, IN-PROGRESS, 2 WEEK WINDOW, and COMPLETED tasks related to that date. Briefly update your project plan by changing the project start date to any day before your cu
ent calendar day, assign each team member to these tasks as resources, update task status as 100% completed (and/or in-progress). (SAVE your project plan file as; [StudentName]_Modified_KBProjectPlan)
· Make sure your primary tasks and sub task are numbered to match the work
eak down structure.
· Only primary tasks should be displayed on the Kanban Board itself.
5. MS Excel Methods and Templates:  If you choose to use MS Excel you can use these instructions; How To Create A Kanban Board In Excel? (With Templates) | ClickUpLinks to an external site., as well as the templates I have placed in the Kanban Board File Folder Download Kanban Board File Folder;  
6. Submit each Kanban Status Board to Canvas using the Kanban Assignment Submission Ta
Include: 
6.
1. 1) Completed Kanban Board file (ideally as separate report generated using MS Project, but otherwise you must be able to display all key Backlog, In Progress, 2 Week Window, and Completed Tasks.  You will only need to display the primary tasks, and maybe some subtasks if they are relevant to project completion.
1. 2) Original .mpp or .xls file (if used) from template with file name as [StudentName Original KBStatusBoard]
1. 3) Modified (using 2 week Agile Sprints and/or reordered based on task priorities and dependencies) .mpp or .xls file from template with file name as [StudentName Modified KBStatusBoard]
6.
 Class Ru
ic - Kanban Status Board - Individual
    Kanban Board - Individual
    Criteria
    Ratings
    Pts
    Kanban Board Required Files
Uploaded to Canvas prior to due date with co
ect naming of all required files for the course assignment website (10 points)
• MS Project Plan Schedule - Original (StudentName_Original)
• MS Project Plan Schedule – Modified (StudentName_Updated)
• Kanban Board File (StudentName_KanbanFinal)
        5 pts
Full Marks
    0 pts
No Marks
    5 pts
    Kanban Board Task List
Demonstrates selection of MS Project or other sourced template that has at least 50+ primary/summary tasks and sub-tasks
        5 pts
Full Marks
    0 pts
No Marks
    5 pts
    Schedule showing Agile Sprints
MS Project Files updated from original to with assigned task leaders for all summary tasks and lower level tasks reordered as appropriate, showing Agile Sprints with Start Finish dates.
        5 pts
Full Marks
    0 pts
No Marks
    5 pts
    Kanban Board Display of Cu
ent Task Status
Kanban Status Board effective in showing summary tasks and key supporting lower level tasks as COMPLETED, IN-PROGRESS and NOT-STARTED tasks (with completion percentages)
        5 pts
Full Marks
    0 pts
No Marks
    5 pts
    Total Points: 20

- MS project Update.mpp
ID Task Name Start Finish Remaining Duration Resource Names Act. Dur. Rem. Dur.
0 Collaborative SBOM Platform and
Vuln. Man. Plan
Mon
10/25/21
Sat 1/29/22 70 days 0 days 70 days
1 Project Scope (Project Charter) Mon 10/25/21 Tue 10/26/ XXXXXXXXXXdays 0 days 1.88 days
2 Determine project scope Mon
10/25/21
Mon 10/25/21 3 hrs Management 0 hrs 3 hrs
3 Secure project sponsorship Mon
10/25/21
Tue 10/26/21 12 hrs Management 0 hrs 12 hrs
4 Define preliminary resources Mon
10/25/21
Tue 10/26/21 12 hrs Project Manager 0 hrs 12 hrs
5 Secure core resources Tue
10/26/21
Tue 10/26/21 0 days Project Manager 0 days 0 days
6 Scope complete Tue 10/26/21 Tue 10/26/21 0 days 0 days 0 days
7 Analysis/Software RequirementsTue 10/26/21 Mon 11/8/ XXXXXXXXXXdays 0 days 9.13 days
8 Conduct needs analysis Tue
10/26/21
Thu 10/28/21 2 days Analyst 0 days 2 days
9 Draft preliminary software
specifications
Thu
10/28/21
Fri 10/29/21 1 day Analyst 0 days 1 day
10 Develop preliminary budget Fri
10/29/21
Mon 11/1/21 1 day Project Manager 0 days 1 day
11 Review software
specifications
udget with team
Mon
11/1/21
Tue 11/2/21 4 hrs Project Manager,Analyst 0 hrs 4 hrs
12 Incorporate feedback on
software specifications
Tue
11/2/21
Wed 11/3/21 1 day Analyst 0 days 1 day
13 Develop delivery timeline Wed
11/3/21
Thu 11/4/21 1 day Project Manager 0 days 1 day
14 Obtain approvals to proceed
(concept, timeline, budget)
Thu
11/4/21
Thu 11/4/21 4 hrs Management,Project
Manage
0 hrs 4 hrs
15 Secure required resources Thu
11/4/21
Fri 11/5/21 1 day Project Manager 0 days 1 day
16 Analysis complete Fri 11/5/21 Fri 11/5/21 0 days 0 days 0 days
17 Design SBOM Software Mon 11/8/21 Wed 11/24/21 13 days 0 days 13 days
18 Review preliminary software
specifications
Mon
11/8/21
Tue 11/9/21 2 days Analyst 0 days 2 days
19 Develop functional specificationsWed 11/10/21 Fri 11/12/21 3 days Analyst 0 days 3 days
20 Develop prototype based on
functional specifications
Mon
11/15/21
Wed 11/17/21 3 days Analyst 0 days 3 days
21 Review functional specificationsThu 11/18/21 Fri 11/19/21 2 days Management 0 days 2 days
Management
Management
Project Manage
10/26
10/26
Analyst
Analyst
Project Manage
Project Manager,Analyst
Analyst
Project Manage
Management,Project Manage
Project Manage
11/5
Analyst
Analyst
Analyst
Management
XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX
November 2021 December 2021 January 2022 Fe
uary 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Collaborative SBOM Pla
Date: Wed 12/8/21
ID Task Name Start Finish Remaining Duration Resource Names Act. Dur. Rem. Dur.
22 Incorporate feedback into
functional specifications
Mon
11/22/21
Mon 11/22/21 1 day Management 0 days 1 day
23 Obtain approval to proceed Tue 11/23/21 Tue 11/23/21 4 hrs Management,Project Manager 0 hrs 4 hrs
24 Design complete Tue 11/23/21 Tue 11/23/21 0 days 0 days 0 days
25 SBOM Platform Development Tue 11/23/21 Fri 12/31/ XXXXXXXXXXdays 0 days28.38 days
26 Review functional specifications Tue
11/23/21
Wed 11/24/21 1 day Developer 0 days 1 day
27 Identify modula
tiered design
parameters
Wed
11/24/21
Thu 11/25/21 1 day Developer 0 days 1 day
28 Assign development staff Thu
11/25/21
Fri 11/26/21 1 day Developer 0 days 1 day
29 Develop code Fri 11/26/21 Mon 12/13/21 11 days Developer 0 days 11 days
30 Developer testing (primary
debugging)
Wed
12/1/21
Thu 12/16/21 11 days Developer 0 days 11 days
31 Develop unit test plans using
product specifications
Thu
12/16/21
Fri 12/17/21 1 day 0 days 1 day
32 Develop integration test plans
using product specifications
Fri
12/17/21
Fri 12/17/21 0 days 0 days 0 days
33 Unit Testing Tue 11/23/21 Fri 12/24/ XXXXXXXXXXdays 0 days22.75 days
34 Review modular code Tue 11/23/21 Thu 11/25/21 2 days Testers 0 days 2 days
35 Test component modules to product specificationsTue 11/23/21 Thu 11/25/21 2 days Testers 0 days 2 days
36 Identify anomalies to product
specifications
Fri
12/17/21
Mon 12/20/21 1 day 0 days 1 day
38 Re-test modified code Mon 12/20/21 Wed 12/22/21 2 days Testers 0 days 2 days
39 Unit testing complete Wed 12/22/21 Fri 12/24/21 2 days Testers 0 days 2 days
40 Integration Testing Fri 12/24/21 Fri 12/31/ XXXXXXXXXXdays Testers 0 days 5.63 days
41 Test module integration Fri 12/24/21 Mon 12/27/21 1 day Testers 0 days 1 day
42 Identify anomalies to
specifications
Mon
12/27/21
Mon 12/27/21 5 hrs 0 hrs 5 hrs
43 Modify code Fri 12/24/21 Mon 12/27/21 1 day 0 days 1 day
44 Re-test modified code Mon 12/27/21 Wed 12/29/21 2 days Testers 0 days 2 days
45 Integration testing completeWed 12/29/21 Thu 12/30/21 1 day Testers 0 days 1 day
46 Product ready for code freezeThu 12/30/21 Fri 12/31/21 1 day Testers 0 days 1 day
47 Documentation SBOM Platform
and VMP
Tue
11/23/21
Wed 1/5/ XXXXXXXXXXdays 0 days 31.5 days
48 Develop Help specification Tue
11/23/21
Wed 11/24/21 1 day Technical Communicators 0 days 1 day
49 Develop Help system Mon
12/6/21
Fri 12/24/21 3 wks Technical Communicators 0 wks 3 wks
Management
Management,Project Manage
11/23
Develope
Develope
Develope
Develope
Develope
12/17
Testers
Testers
Testers
Testers
Testers
Testers
Testers
Testers
Technical Communicators
Technical Communicators
XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX
November 2021 December 2021 January 2022 Fe
uary 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Collaborative SBOM Pla
Date: Wed 12/8/21
ID Task Name Start Finish Remaining Duration Resource Names Act. Dur. Rem. Dur.
50 Review Help documentation Mon
12/27/21
Wed 12/29/21 3 days Technical Communicators 0 days 3 days
51 Incorporate Help
documentation feedback
Thu
12/30/21
Fri 12/31/21 2 days Technical Communicators 0 days 2 days
52 Develop user manuals
specifications
Tue
11/23/21
Thu 11/25/21 2 days Technical Communicators 0 days 2 days
53 Develop user manuals Mon
12/6/21
Fri 12/17/21 2 wks Technical Communicators 0 wks 2 wks
54 Review all user documentation Mon
12/20/21
Tue 12/21/21 2 days Technical Communicators 0 days 2 days
55 Incorporate user documentation
feedback
Wed
12/22/21
Thu 12/23/21 2 days Technical Communicators 0 days 2 days
56 Documentation complete Fri
12/31/21
Fri 12/31/21 0 days 0 days 0 days
57 Vulnerability Manament Plan Mon 11/8/21 Fri 1/7/ XXXXXXXXXXdays 0 days44.75 days
58 Define and document the plan Mon 11/8/21 Tue 11/9/21 12 hrs Project Manager 0 hrs 12 hrs
59 Define measures of effectivenessTue 11/9/21 Wed 11/10/21 12 hrs 0 hrs 12 hrs
60 Determine tools aligned to the
strategy
Mon
1/3/22
Mon 1/3/22 1 day Deployment Team 0 days 1 day
61 Identify sources of vulnerability
information
Tue 1/4/22 Tue 1/4/22 1 day 0 days 1 day
62 Define the roles and responsibilitiesWed 1/5/22 Wed 1/5/22 1 day 0 days 1 day
63 Engage stakeholders Thu 1/6/22 Thu 1/6/22 1 day 0 days 1 day
64 Develop a plan revision process Fri 1/7/22 Fri 1/7/22 5 hrs Deployment Team 0 hrs 5 hrs
65 VMP complete Fri 1/7/22 Fri 1/7/22 0 days 0 days 0 days
66 Deployment Fri 1/7/22 Tue 1/25/22 13 days 0 days 13 days
67 Determine final deployment
strategy
Mon
1/10/22
Mon 1/10/22 4 hrs Deployment Team 0 hrs 4 hrs
68 Develop deployment methodologyMon 1/10/22 Tue 1/11/22 5 hrs Deployment Team 0 hrs 5 hrs
69 Secure deployment resources Tue 1/11/22 Wed 1/12/22 8 hrs Deployment Team 0 hrs 8 hrs
70 Train support staff Wed 1/19/22 Tue 1/25/22 40 hrs Deployment Team 0 hrs 40 hrs
71 Deploy software Tue 1/25/22 Tue 1/25/22 0 days Deployment Team 0 days 0 days
72 Deployment complete Tue 1/25/22 Tue 1/25/22 0 days 0 days 0 days
73 Post Implementation Review Tue 1/25/22 Sat 1/29/22 5 days 0 days 5 days
74 Document lessons learned Wed 1/26/22 Wed 1/26/22 1 day Project Manager 0 days 1 day
75 Distribute to team members Thu 1/27/22 Thu 1/27/22 1 day Project Manager 0 days 1 day
76 Create software maintenance teamFri 1/28/22 Fri 1/28/22 1 hr Project Manager 0 hrs 1 h
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
12/31
Project Manage
Deployment Team
Deployment Team
1/7
Deployment Team
Deployment Team
Deployment Team
Deployment Team
1/25
1/25
Project Manage
Project Manage
Project Manage
XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX
November 2021 December 2021 January 2022 Fe
uary 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Collaborative SBOM Pla
Date: Wed 12/8/21
ID Task Name Start Finish Remaining Duration Resource Names Act. Dur. Rem. Dur.
77 Post implementation review
complete
Fri 1/28/22 Fri 1/28/22 1 hr 0 hrs 1 h
78 Web-base collaborative platform
complete
Fri 1/28/22 Fri 1/28/22 0 days 0 days 0 days 1/28
XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX XXXXXXXXXX
November 2021 December 2021 January 2022 Fe
uary 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Collaborative SBOM Pla
Date: Wed 12/8/21
Answered 3 days After Nov 10, 2023

Solution

Shubham answered on Nov 12 2023
25 Votes
SOLUTION.PDF

Answer To This Question Is Available To Download