Please use Microsoft Project, and follow the rubric

1 answer below »
PART 1
Frankie & Co to Open a New Bakery
Frankie and Charlie recently a completed a degree in Culinary Arts, with a specialty in baking. They decide to start a business, Frankie & Charlie Bakes (F&CB) to make their own baked goods. They decide to differentiate themselves from the competition by producing sustainably sourced ingredients, using environmentally conscious manufacturing techniques.
After conducting a series of market research studies, they decide to introduce a line of products that are based on flavours from around the world. The taste,
anding and name of the products will be based on specific regions in the world that they have visited over the years.
Your team has been hired to assist them in setting-up the new bakery. They need your help to build a plan to start the bakery.
Your team has completed the WBS, Precedence Table and identified the Critical Path with the Network Diagram. Your team met with Frankie and Charlie to review the work and get agreement to move to the next step in the engagement – preparing the project schedule.
Frankie and Charlie have also provided your team with the following information:
· They want to start this project on January 09, 2023 with a maximum budget of
$250,000 (CAD) and needs to be completed within 4-months.
· January 12 to 13 will be an offsite meeting that you and all other resources need to attend, so no work will take place during these days
· No work on the weekends
· Frankie and Charlie have asked you to include all the project management work required to complete the project in the schedule and identify the related costs i.e., WBS, Precedence Table and Network Diagram.
Deliverables: Due April 11, XXXXXXXXXX:00 PM EST)
You need to prepare a project schedule to track and manage the work. The project schedule will be used to determine the costs and report on the progress. The project schedule needs to include the following components:
· Summary level information of the work
· Task level information of the work
SCHEDULE & COST MANAGEMENT: Assignment 2
· Start & Finish dates for each task
PAGE 2
MGMT 4085
· The amount of time required to complete each task (duration)
· Include predecessors and milestones
· Identification of the critical activities illustrated in the GANTT chart and schedule
· Assign resources and costs for all activities
· Set Project Baseline
Grading:
· Grading of the Assignment will be based on the following criteria for a total of 15 points.
    Criteria
    Points
    Â· Identification of Summary Tasks (Level 2)
· Identification of Task Level work (Level 3, 4 etc.)
· Duration of the Tasks
· Accuracy of the Start & Finish dates based on
· Project Start Date
· Non-Working Time
· Holidays
· Identification of milestones
· Identification of predecessors (dependencies)
· Identification of the critical activities
· Identification of costs
· Alignment budget
· Consistency of project schedule with the Network Diagram
    
    
    
    
    
    
    
    
    15
    
    
    
    
    
    
    
    
    
    
    -    Manual scheduling of tasks
    -5
    -    Not showing Entire Project with Gantt chart
    -5
PART 2
Frankie & Co to Open a New Bakery
Frankie and Charlie recently a completed a degree in Culinary Arts, with a specialty in baking. They decide to start a business, Frankie & Charlie Bakes (F&CB) to make their own baked goods. They decide to differentiate themselves from the competition by producing sustainably sourced ingredients, using environmentally conscious manufacturing techniques.
After conducting a series of market research studies, they decide to introduce a line of products that are based on flavours from around the world. The taste,
anding and name of the products will be based on specific regions in the world that they have visited over the years.
Your team has been hired to assist them in setting-up the new bakery. They need your help to build a plan to start the bakery.
Your team has completed the WBS, Precedence Table and identified the Critical Path with the Network Diagram. Your team had a meeting with Frankie and Charlie to review the work when they advised you of the budget, timelines and details regarding working time. Frankie and Charlie set a maximum budget of $250,000 (CAD) and a timeline of
4-months to complete the project. Based on information provided in the meeting your team prepared a project schedule (using MS Project).
Since completing the project schedule, 2-months have passed, and Frankie and Charlie have contacted you with an update. They advise you that there are potential investors in their bakery. This is good news for Frankie and Charlie. Before the investors commit funding, they need to receive an update on the project. The investors are also interested in adding a new line of products to the baked goods.
2- Month Update*
a) Set-up of the location (online or physical) is complete, however, total amount of time required 5-additional days.
) Product Testing is taking longer than expected, since it’s difficult to get the appropriate sample size of customers. Testing of the product is now 7-days behind schedule.
c) Development of the marketing tactics are now 75% complete.
d) Selection of the Equipment is complete, however, delivery and installation is 7- days delayed
e) People work package was completed earlier than planned, with all tasks completed 5-days ahead of plan
* Ensure the Baseline is set before making any updates to the project
New Product Line
The new product line will introduce premium goods that will be sold for a higher margin compared to other goods. These goods will require specialized equipment and ingredients.
· A baker with specialized knowledge will be needed to prepare the new goods.
The cost for this baker is expected to be 10% more than the salary of the ‘regular’ baker, however, this baker is only needed 25% of the time.
· The new equipment cost an additional $5,000 and ingredients costs an additional $1,000
· Testing of the new product line will require a separate series of testing and take 7-days to be completed. This additional round of testing needs to be complete before all products can be commercialized.
· No other impacts to the business are expected based on the new product line
Deliverables: April 13, XXXXXXXXXX:00 PM EST)
The following is needed to prepare for the meeting with the new investo
1. Updated MS Project Schedule includes 2-Month Updates and The New Product Line
2. Prepare a PowerPoint Presentation with the following information: Part 1: 2-Month Update (2-3 slides)
a. Update on the cu
ent status of the project schedule and budget illustrating plan vs. actual, including update on the Critical Path and Tracking Gantt (refer to Project Statistics), including sections of the project that are either late
. Update on Project Milestones Part 2: New Product Line (2-3 slides)
a. Assessment of the impact to the project (schedule and budget) due to New Product Line, including update on the Critical Path and Tracking Gantt
. Update on Project Milestones
Grading:
· Grading of the Assignment will be based on the following criteria for a total of 15 points.
    Criteria
    Points
    Updated Project Schedule which includes:
    
    Â· Finalized Baseline
    
    Â· Progress based on 2-month update
    
    Â· New Product Line changes
    10
    Â· Include any leads or lags (at least 1 of each)
    
    Â· Includes at least 1 constraint/deadline (needs to be logical)
    
    Â· Include at least 1 recu
ing task
    
    PowerPoint Presentation including:
    
    Â· Part 1 – 2-month status update
    2.5
    Â· Part 2 – New Product Line assessment
    2.5
    Total
    15
    Deductions
    
    Â· Manual scheduling of tasks
    -2.5
    Â· Not showing Entire Project with Gantt Chart
    -2.5
    Â· Status Update line not showing
    -2.5
    Â· Overallocations
    -2.5
    Up to -5 marks for each of the previous criteria from Assignment 2 that is
    
    not included
    
    Â· Identification of Milestones
    
    Â· Identification of predecessors (dependencies)
    
    Â· Identification of critical activities
    
    Â· Identification of costs
    

Assignment 2
    Precedence Table
                            Rawand
    Task ID    WSB #    Task Name    Predecessor    Duration (Days)        Resource    Cost    Milestone (Y/N)
            Sales & distribution
    A    1.1    Research online options    None    5
    B    1.2    Research store front options    None    5
    C    1.3    Evaluate pros and cons of each options    1,2    2
    D    1.4    Make final decision    3    2
            People
    E    2.1    Hire planning    4    3
    F    2.2    Hire initiation    5    4
    G    2.3    Hire execution    6    20
            Procurement
    H    3.1    Planning    4    3
    I    3.2    Intiating    8    4
    J    3.3    Puchasing    9    9
            Product development
    K    4.1    Create prototype    None    6
    L    4.2    Test product    11    10
    M    4.3    Commercialize product    12    6
            Marketing
    N    5.1    Identify customer segments and target audience    13    5
    O    5.2    Determine marketing tactics    14    7
    P    5.3    Develop
anding    15    16
Part 2 - Precedence table
    Precedence Table
    Task ID    WSB #    Task Name    Predecessor    Duration (Days)
            Sales & distribution
    A    1.1    Research online options    None    5
    B    1.2    Research store front options    None    5
    C    1.3    Evaluate pros and cons of each options    1,2    2
    D    1.4    Make final decision    3    2
            People
    E    2.1    Hire planning    4    3
    F    2.2    Hire initiation    5    4
    G    2.3    Hire execution    6    20
            Procurement
    H    3.1    Planning    4    3
    I    3.2    Intiating    8    4
    J    3.3    Puchasing    9    9
            Product development
    K    4.1    Create prototype    None    6
    L    4.2    Test product    11    10
    M    4.3    Commercialize product    12    6
            Marketing
    N    5.1    Identify customer segments and target audience    13    5
    O    5.2    Determine marketing tactics    14    7
    P    5.3    Develop
anding    15    16
Part 2 - Network Diagram
                0    A    5        5    C    7        7    D    9        9    E    12        12    F    16        16    G    36
                14        14        14        14        14        14        14        14        14        14        14        14
                14    5    19        19    2    21        21    2    23        23    3    26        26    4    30        30    20    50
                0    B    5                                        9    H    12        12    I    16        16    J    25
        START        14        14                                        25        25        25        25        25        25        FINISH
                14    5    19                                        34    3    37        37    4    41        41    9    50
                0    K    6        6    L    16        16    M    22        22    N    27        27    O    34        34    P    50
                0        0        0        0        0        0        0        0        0        0        0        0
        Late finish =     50    0    6    6        6    10    16        16    6    22        22    5    27        27    7    34        34    16    50
            
            Critical Path
            The critical Path in this case is K -L - M- N - O - P because it will take the longest amount of time to complete. It will take 50 days to be completed.
            Slack
            We can see that task K,L,M,N,O and P have no slack because they are on the critical path. They must be completed on time or it will delay the project.
            Task A, B, C, D, E , F , G, H, I and J have some slack meaning the project can be delayed without disrupting the overall project.
Part 1 - WBS Final
    Frankie & Co to Open a New Bakery
    Schedule & Cost Management: Assignment 1
    Project Deliverables (WBS)
    1 Sales & distribution
        1.1 Research online options
        1.2 Research store front options
        1.3 Evaluate pros and cons of each options
        1.4 Make final decision
    2 People
        2.1 Hire planning
            2.1.1 Determine positions to be hired
            2.1.2 Determine number of positions to be filled
        2.2 Hire initiation
            2.2.1 Write job descriptions for each position needed
            2.2.2 Determine qualifications needed
            2.2.3 Create/post a job announcement
        2.3 Hire execution
            2.3.1 Screen resumes
            2.3.2 Book interviews
            2.3.3 Choose the best candidate
            2.3.4 Send job offe
            2.3.5 Onboard employees
    3 Procurement
        3.1 Planning
            3.1.1 Determine equipment/materials needs
            3.1.2 Determine equipment/materials requirements
            3.1.3 Search for suppliers
        3.2 Intiating
            3.2.1 Request quotes for purchasing/leasing
            3.2.2 Evaluate purchasing option
            3.2.3 Evaluate leasing option
        3.3 Puchasing
            3.3.1 Decide on the option/supplie
            3.3.2 Sign purchase/lease agreement
            3.3.3 Provide deposit if needed
            3.3.4 Get items delivered
    4 Product development
        4.1 Create prototype
        4.2 Test product
        4.3 Commercialize product
    5 Marketing
        5.1 Identify customer segments and target audience
        5.2 Determine marketing tactics
        5.3 Develop
anding
Answered Same Day Apr 09, 2023

Solution

Banasree answered on Apr 10 2023
25 Votes
Part 1
Summary level information:
The project involves sales and distribution planning, research on online and store-front options, evaluation of pros and cons, decision-making, hiring planning and execution, procurement, equipment and material requirements determination, supplier search, purchasing and leasing evaluation and execution, product development, and marketing. The project has a duration of 148 days, starting on January 9, 2023, and ending on July 6, 2023.
Task level information:
1. Sales & Distribution (14 days)
a. Frankie & Charlie assigned to the task (10%)
2. Research online option (5 days)
3. Research store-front option (5 days)
4. Evaluate pros and cons of each option (2 days)
a. Task requires input from two team members (2,3)
5. Make final decision (2 days)
6. People (27 days)
a. Frankie & Charlie assigned to the task (10%)
. HR manager assigned to the task (10%)
7. Hire planning (3 days)
8. Hire initiation (4 days)
9. Hire execution (20 days)
10. Procurement (10 days)
a. Frankie & Charlie assigned to the task (10%)
11. Planning (5 days)
12. Determine equipment/materials needs (3 days)
13. Determine equipment/materials requirements (2 days)
14. Search for supplie
15. Initiating (5 days)
16. Request quotes for purchasing/leasing (2 days)
17. Evaluate purchasing option (2 days)
18. Evaluate leasing option (1 day)
19. Purchasing (3 days)
a. Frankie & Charlie assigned to the task (15%)
20. Decide on the option/supplier (1 day)
21. Sign purchase/lease agreement (1 day)
22. Provide deposit if needed (1 day)
23. Get items delivered (1 day?)
24. Product development (25 days)
a. Baker assigned to the task (10%)
25. Create prototype (15 days)
26. Test product (5 days)
27. Commercialize product (5 days)
28. Marketing (35 days)
a. Marketing Manager assigned to the task (15%)
29. Identify customer...