Hello, there are 3 assignments in the pdf instruction attached, however we are only doing assignment 1 for this case. I made the deadline short because, this assignment is already finished. a friend...

1 answer below »
Hello, there are 3 assignments in the pdf instruction attached, however we are only doing assignment 1 for this case. I made the deadline short because, this assignment is already finished. a friend of mine got it done on your webstie but i had a look and i want to it be changed around so that i dont get caught plagiarizing. I hope you can help me with this today so i can hand it in as it is due in avbout 12 hours. the first part will require a gantt chart. please create a new gantt chart with a similar structure to the one found in the screen shot in the word document. and do the same for the next tasks. please redo same tasks in a different way on excel and let me know how long it will take:)). im in a rush so i will appreicate all
Answered Same Day Aug 23, 2021 University of Southern Queensland

Solution

Ishwar answered on Aug 25 2021
104 Votes
Construction surveying 1
Construction surveying
Student Name
Student Roll No:
Assignment 1.a
Gantt chart :

Critical path diagram:
Critical path : A-D-F-G-I-L-M-M-O
Duration : 0+2+8+9+3+4+3+1+0 = 30 days
Total float = critical path duration-duration of non-critical path
Non-critical path = A-D-F-J-K-O-P = 0+2+8+6+3+4+0 = 23 days
Total float = 30-23 = 7 days
Assignment 1.b
1.
In construction sector, there are mainly two types of contract: 1. Lump sum contracts 2. Schedule of rates contracts.
As there is competition in the prices amongst contractors then these two contracts usually applied and uses. There are mainly two aspects and situations provided and select the suitable contract to manage complete work.
a. Supply three robotic total stations plus specified associated equipment
In this case, the employees need to deliver or supply equipment that means it demand transportation and machine delivery management system. in this case, the management contract is most suitable by considering situation. in this case, the employer may interest a contract for the specific activity and entire performance of the project. the specific unit or small size organization may undertaking the work which must ca
ied out all those functions either using own resource or specialist.
Under this situation, the contractor or company is responsible for the specific project in its entirety and the project manager. In this case, the tender...