Basic Scenario for all questions: A major industrial site has decided to significantly upgrade an existing process water treatment plant (Note: There are no human waste or public health wastewater...

1 answer below »
Basic Scenario for all questions: A major industrial site has decided to significantly upgrade an existing process water treatment plant (Note: There are no human waste or public health wastewater issues with this treatment plant). The client's budget is $349,400 + GST. The upgrade project has the following objectives: 1 Improve the quality of the treated water discharged to the nearby stream by the replacement of worn out pumps and other mechanical equipment to change hydraulic flow through the plant by the alteration of some of the pipework and the installation of computer control to replace the current manual process; and 2 To provide an new telemetry system to allow off site monitoring, of the plant operations, by the Client / Principal . The Principal has engaged a firm of Professional Engineers to prepare contract documents for the project with the following contract description: This contract covers a mixture of mechanical, electrical and civil remedial works plus upgraded monitoring installation at the existing water treatment plant at Clutha (CTP). This plant is owned by XYZ Ltd and is currently operated by a Contractor, ABC Ltd. Examples of the relative types of works are: A Remedial Works Clean and paint pipework, remove and recondition dosing pumps and / or discharge nozzles, bird-proof plant rooms, electrical testing of both motors and variable drive units,; and B Improved Install turbidity meters; supply and install new streaming Monitoring current meters., data stations with radios The purpose of the water treatment plant is to treat contaminated process water to a Resource Consent Standard, suitable for discharge to adjacent stream. The estimated duration for the work is 7 weeks total. This contract is a Measure and Value contract. This contract is provided to selected tenderers (3) only. At the end of the tender period three tenders have been received. The tenders were: 1. LMN Ltd was $ 362, 176 +GST and included 8 tags , 2. PPK Ltd was $ 365,000. + GST and included 20 tags ; and 3. ZXK Ltd was $ 355,458 +GST and included 3 tags , one of which required the Client ( XYZ Ltd) to take 100% RESPONSIBILITY FOR COMMISSIONING You are the project manager/ Engineer to Contract and you are responsible for either dealing with the following issues (if you have the authority) OR advising the Principal / Client what action should be taken. QUESTION ONE ADMINISTRATION OF CONTRACTS XXXXXXXXXXGiven that the tender exceeds the Principal's budget you contact the ELECTRICAL Consultant to investigate whether or not there are cheaper plant items that can achieve the project objectives. Should any tenderer be involved in this process as they may have some good ideas to reduce the gap between tender and budget? Give at least two reasons for your choice. (3 marks) Your Electrical consultant advises that existing mixers can be fitted with reconditioned electric motors to give a net saving on the tender schedule of $28,400. Write a brief email, of no more than 150 words, to the tenderers explaining how you wish to change the scope of the tender and reduce the tender amount by $28, XXXXXXXXXXmarks) State any legal basis for your plan of action. (1 mark) You have assessed the 8 tags from LMN Ltd and 12 of the 20 Tags from PPK Ltd and feel that these tags can be accepted without any issue. Eight (8) remaining tags from PPK Ltd tags are minor and should be able to be negotiated at a pre-contract meeting. However, the remaining three(3) major tags from ZXK Ltd relate to contract duration and to get these settled the Principal might need to extend the contract period from seven (7) weeks, as specified in the tender document, to twelve (12) weeks. You are to recommend one of these tenderers to your client. Write a letter not exceeding 150 words recommending one of the three tenderers to your client and explain your reasons for this recommendation ( 3 marks) Write a draft letter, of no more than 250 words (one page), which invites your recommended tenderer to a pre-contract meeting. In the letter you will need to give some indication as to how the tags will be dealt with. You will also need to provide an agenda for the meeting, which is to be attached to the letter. (3 marks) The pre-contract meeting and resolution of the major tags was successful. LMN Ltd now agrees to submit a revised tender of $333,776 + GST ( LMN Ltd agreed to the reduction in scope of this tender). The Principal has also agreed to extend the contract period to twelve (12) weeks. Write a brief letter, on behalf of XYZ Ltd, of no more than 160 words, to LMN Ltd accepting the revised tender amount with the revised contract period. (6 marks) (Total 20 marks) QUESTION TWO PROCESSING PAYMENT CLAIMS In a continuation of the treatment plants upgrade scenario, physical works get underway in mid April XXXXXXXXXXYou receive the first claim from LMN Ltd on 1 May 2004. At the pre-contract meeting you had asked LMN Ltd to give you a cashflow forecast (this was recorded in the minutes of the meeting). LMN Ltd has failed to provide this forecast. In your opinion LMN Ltd has completed 5%-10% of the contract. LMN Ltd's claim is $38,000 + GST and is made under the Construction Contracts Act 2002 and General Conditions of Contract NZS XXXXXXXXXXNo specific terms for payment were agreed at the pre-contract meeting. How much do you think LMN Ltd should be paid? What are your reasons for this view? (2 marks) Outline the process of payment claims and payment schedules with the various time limits clearly stated (you may use a flow chart diagram if you wish). (5 marks) You receive the fourth claim for payment from LMN Ltd on Monday 3 October 2004 for $42,990 + GST. So far you have spent $286,00 of the $333,776 agreed contract price. However, you are aware that XYZ Ltd has been to LMN Ltd directly and that there may be approximately $10,000 of unapproved variation. You discuss the fourth claim with the Principal. They tell you to pay the claim, so you prepare a payment schedule which you send to both LMN Ltd and XYZ Ltd on Friday 21 October 2004 Are you within the legal time limit given in NZS3910:2003? Justify your answer. (2 marks) XYZ Ltd now has five (5) working days to pay LMN Ltd — Yes or No? (1 mark) In this period, after three (3) days, the Principal notices that LMN Ltd has claimed for the same turbidity meter twice (value $7,000). The Principal refuses to pay twice for the same item and tells you to deduct $7000 from this payment. Can the Principal or the Engineer to Contract do this? Provide your reasoning. (5 marks) (Total 15 marks) 3 QUESTION THREE EXTENSION OF TIME CLAIMS XXXXXXXXXXThe contract physical works commenced in mid April 2004 and by mid May 2004 LMN Ltd had commenced earthworks around both the settlement pond and the treatment plant building. In late May 2004 your engineer's representative tells you that he has had to warn the LMN Ltd about leaving the earthworks site in a mess over the last two weekends and that the earthworks subcontractor appears to be ignoring Environmental Management Plan and Quality Plan that all parties had agreed to at the pre-contract meeting seven (7) weeks ago. That weekend it rains heavily and the exposed site floods and turns to mud. The subcontractor is unable to work for a week until the mud dries out. Two days after this weekend LMN Ltd asks for one week Extension of Time (“EOT”) and indicates that it may want a variation to get rid of the dried mud. Write a note, of no more than 160 words, as to how the Principal and Engineer should respond to the EOT request. Quote the relevant clauses of NZS 3910:2003 in support of your response. Also indicate whether you agree with the variation (you do not need to provide reasons for your decision). (8 marks) Later in the contract period (July 2004) LMN Ltd is undertaking its specialty work, such as computer controls, electrical work and the installation of flow meters. Given its expertise LMN Ltd has made up for the time lost in May 2004. The Principal then thinks it would be a good idea to put in duplicate electronic control panels to allow for a future upgrade to the plant. LMN Ltd says it can do this extra work as an approved variation for an additional $10,000 but is not keen to commit to a fixed duration. However, LMN Ltd would agree to the contract finish date being extended for another six (6) weeks. The Principal agrees to the $10,000, but given that the first electronic control panel installation only took one (1) week, the Principal believes LMN Ltd should only get an EOT of one (1) week or two (2) weeks maximum. Can you make LMN Ltd do the variation for a one (1) or two (2) week EOT? Explain your reasons referring to NZS 3910: XXXXXXXXXXmarks) Can LMN Ltd decide to reject this request for a variation and not be penalised? Explain your answer, with reference to NZS 3910:2003.
Answered Same Day Dec 22, 2021

Solution

Robert answered on Dec 22 2021
130 Votes
Solution
Q1.1- Contractor must be involved with the consultant to generate ideas for reducing
the gap between tender amount and budget amount. Following are the 2 main reasons-
1. Vendors can verify and validate the propose ideas of using alternative cheaper
component for its manufacturability as well as its availability with timeline of
procurement. They can also check technical constraints present in their technical
setup as well as sub contractor technical setup for development of alternative
component. They can also provide a view of cost increase due to propose
change versus cost decrease due to use of alternative cheaper component.
2. Vendors must be having experience to work on similar kind of projects and can
provide many valuable ideas for value engineering. After visualizing the actual
plant and requirement of component with respect to plant, they can revisit to the
specifications given to them and may propose some changes in the specification
within all the quality and safety envelope and would able to identify the areas of
cost saving.
However in this exercise, involved vendors should not get a clue about the
udget of project.
Q1.2- e-mail
Dear Contractor,
Attention: Mr./Ms.
Dear Si
Madam,
Decision on the basis of negotiated variation:
Here we are changing the scope of tender requirement under the section 9 of NZS
3910:2003. We are changing the scope of the project by fitting the existing mixers with
econditioned electric motors; It is estimated that, this change in scope will reduce the
cost of Project by around $28,400.
We want to revise the contract agreement of the project by changing the scope of the
project. It should also be noted that the general obligation on the contractor under NZS
3910:2003. Clause 9.2.2 and 9.5.3 still ca
ies on. We would like from you to validate
the above change at your working level and revise your tender accordingly?
Our expectation is to reduce your tender by at least amount of $28,400.
Yours Faithfully.
Enginee
Q1.3- Recommendation Letter for finalizing Tender
Dear Mr. XXX
We have evaluated the tenders of below three companies-
1. LMN Ltd.
2. PPK Ltd.
3. ZXK Ltd.
Our recommendation is to accept the tender of LMN Ltd. Below are the main reasons
ehind my recommendation-–
1. The tender of ZXK Ltd is having a Tag which explained that the complete
esponsibility of commissioning is lying with you, which certainly is not an
acceptable clause for you as we have to create sufficient infrastructure for
commissioning. Also we have to make sure that sufficient process and
procedures are in place to manage it effectively.
2. The price quoted in the tender of LMN Ltd is lesser than the price quoted in the
tender of PPK Ltd.
3. All the 8 Tags in the tender of LMN Ltd are acceptable without any issue however
8 tags out of total 20 tags in the tender of PPK Ltd are required some discussion.
However it is not a major setback in the tender of PPK Ltd.
4. The project duration is also increasing significantly in case of ZXK Ltd, however
their price is lesser than LMN Limited. Considering the very small difference in
the price quotation and higher difference in Project schedule, we will not
ecommend the ZXK Ltd.
Below is the draft letter to invite the tenderer in pre-contract meeting.
Dear Contractor,...