Based on the information contained in the Ariba Case, complete the template (AribaStudent.xls) andsubmit the template along with short answers(3-5 sentences) to the following questions. What is...

1 answer below »


Based on the information contained in the Ariba Case, complete the template (AribaStudent.xls) andsubmit the template along with short answers(3-5 sentences) to the following questions.




  1. What is preventing the project from hitting the original October 1 go-live date?


  2. Why didn’t Terry notice earlier?


  3. What should the PM have done differently?


  4. What should the PM do going forward?
    NB: The "rolling status" is the cumulative status of the project to-date. For May, the rolling status is the same as monthly status. For June, it's May + June. For July, it's May + June + July, etc.
    Protip: You can copy a COLUMN of values in Excel and paste them as a ROW of values by right-clicking in the cell you are pasting into, and then choosing "Paste Special >> Transpose."


Answered Same Day Feb 18, 2023

Solution

Banasree answered on Feb 19 2023
33 Votes
1.Ans.
Based on the provided data, there are a few factors that may be preventing the project from hitting the original October 1 go-live date.
1. There are significant cost ove
uns in both the Technical Infrastructure and Software Customization plans.
2. Additionally, the actual performance data shows that the project is falling behind schedule, with BCWP consistently lower than BCWS. These factors suggest that the project is facing delays and cost issues, which could be preventing it from hitting its original go-live date.
3. Further analysis would be needed to determine the specific causes of these issues and to develop a plan to get the project back on track.
2.Ans.
It's difficult to determine from the provided data why Te
y didn't notice the issues with the project earlier.
· However, it's possible that there were communication
eakdowns or reporting issues that prevented Te
y from being aware of the full scope of the project's delays...