ASSESSMENT TASK
Australian BUSINESS & BUILDING DISPUTES
Refer to Material attachments
A short introduction for each question and then list answer in point
form.
Provide copies of the documentation that would be used for each
question.
1. Procedures that are in place to avoid Building disputes in Australia
2. Dean is a carpenter who installed cabinets in the kitchen of a
esidential home. Dean has submitted a claim for payment under
his subcontract to the builder but has not received payment within
the 10 days required under his agreement.
• In point form prepare a procedure to resolve this dispute with the Client
• Provide a
ief description of the dispute and how and why it occu
ed
3. Adrian subcontracted to a local builder (Principal Contractor) to
install a new roof on a residential house in Brisbane, QLD . After the
contract was completed, the builder notified Adrian of a water leak in
the lounge area of the house. Adrian has inspected the work and does
not believe he is responsible for the roof leak.
• In point form prepare a procedure to resolve this dispute with the Client
• Provide a
ief description of the dispute and how and why it occu
ed
4. In point form provide a step by step process if a building dispute in Australia cannot be resolved and
the issue ends up in a tribunal or hearing.
5. In point form provide a procedure to monitor and evaluate the procedures on a regular
asis.
Handling customer complaints
Dealing with a complaint is never easy, but if viewed positively, it can be seen as a way to
avoid a repeat of the problem.
It’s never a good idea to ignore the complaint. You'll quickly reach a resolution if you try and
understand the customer's point of view.
Don’t be afraid of complaints. For each customer whose complaint you handle well, most will
emain loyal and recommend you to other potential customers.
Tips to avoid complaints
▪ record complaints – even if they are ve
al
â–ª act promptly
▪ do what you say you’re going to do
▪ don’t make unrealistic promises.
Guide to resolving complaints
1. Deal with the complaint immediately. Get to the heart of the matter quickly,
and you’re more likely to satisfy the customer. Ignoring it will not solve the
problem.
2. Stay calm. The customer must be dissatisfied for some reason, even if you
think they are wrong. The matter will only get worse if you respond
aggressively.
3. Identify the problem. Listen to what the customer says and make sure you
understand. Ask what they expect you to do, and write it down in as much
detail as possible.
4. Decide what can be done. Even if you believe the complaint is unjustified, it
may be worthwhile trying to make the customer happy to keep their business.
All it may require is a simple explanation. Sometimes it is worth ‘walking the
extra mile’, and doing more than you feel you need to, or are obliged to, for
the customer.
5. A
ange a second opinion to confirm your view. In some instances this
second opinion may show up things you hadn’t noticed.
6. Keep records. Writing everything down reduces the chance of
misunderstanding. Many contractual disputes arise because nothing is in
writing, or the details are ambiguous.
7. Fix the problem. Tell the customer what solution you can offer and make
sure they understand. If they accept the solution, act straight away and
esolve the matter quickly and efficiently.
Our role in complaints
Once a homeowner or a body corporate lodges a defective work complaint, we may provide
a dispute resolution service between licensees and homeowners. We also offer an Early
Dispute Resolution (EDR) service if you are still under contract.
https:
www.qbcc.qld.gov.au/defective-work-disputes/complaints-your-contract-has-been-completed
https:
www.qbcc.qld.gov.au/defective-work-disputes/complaints-your-contract-has-been-completed
Process after complaint made to QBCC -
1. Application – If you have submitted your complaint online, you'll receive an
automatic email response which provides your unique case number. You can refer
to this if you need to contact us.
2. Assessment – A QBCC Resolution Services officer will assess your submission and
contact you and the contractor to discuss the complaint and obtain further information
or documents if required.
3. Access – You will be asked to give access to the contractor to inspect and assess
the items. Choosing not to give access will have a big impact on how we can help
you. We will not be able to direct the contractor to fix any defective items. This can
also impact your ability to make a claim under the Queensland Home Wa
anty
Scheme.
4. Owner and contractor meet to resolve items – You meet the contractor on site to
eview each item and decide a plan for the repair of any agreed items.
5. Repairs – The contractor ca
ies out all agreed repairs.
6. Inspection – When conducting an inspection, the QBCC Building Inspector will ca
y
out a visual inspection only. This will involve visually observing each complaint item.
Invasive investigations are not undertaken by the QBCC to determine the cause of
an alleged defect. Examples of invasive investigations include cutting a hole in a wall
to look at damage behind the wall. The inspection is also not intended to be a
complete inspection of the whole building or dwelling.If there are any defective
workitems which cannot be resolved, a QBCC Building Inspector is assigned to the
case and will contact you and the contractor to attempt to facilitate an outcome. If this
is unsuccessful, the QBCC Building Inspector may undertake a site inspection.
7. Resolution – Following a site inspection, we may issue a Direction to Rectify to the
contractor, and any relevant subcontractors, to rectify defective building work. In
most cases, this requires a 28-day minimum rectification period. We have no power
to issue a direction for items that are not defective building work, please
see Complaints about your contract. In the case where a contractor fails to comply
with a direction, they can receive a fine or be prosecuted. The case may then be
assessed for a possible claim under the Queensland Home Wa
anty Scheme
(applies to work covered by the Scheme). If a claim is approved, we will recover the
cost from the contractor.
Assistance under Queensland Home Wa
anty Scheme
Should your complaint involve residential construction work and is not able to be
satisfactorily resolved through QBCC’s dispute resolution process, your application will be
assessed as to whether you may be eligible for assistance under the Queensland Home
Wa
anty Scheme. You are not required to lodge a separate form for this to occur. If a claim
is approved, we will recover the cost from the contractor.
Please note the following strict time limits apply for some claims:
â–ª For structural defects you must apply within 3 months of noticing the defect
â–ª For non-structural defects you must apply within 7 months of the completion date.
https:
www.qbcc.qld.gov.au/defective-work-disputes/defective-work
https:
www.qbcc.qld.gov.au/defective-work-disputes/defective-work
https:
www.qbcc.qld.gov.au/download-free-national-construction-code
RESOLVING DISPUTES
AVOIDING THE DISPUTE
Avoiding a dispute needs you to focus on communication as the basis for
identifying, and avoiding conflict.
Poor communication is a major source of conflict so give this serious attention
efore you start the project work. Ask yourself:
â–ª Who needs to know?
â–ª What do they need to know?
â–ª How much do they need to know?
â–ª How often must they be informed?
Establish distribution list(s) as appropriate but avoid generating large volumes of
paper. Decide the ground rules you will impose on everyone to get prompt feed
ack to the prevailing situation with the work in progress. Effective monitoring
and tracking of the project is dependent on good communication in the team,
etween you and the team and your key stakeholders. You need prompt
feedback about:
â–ª Cu
ent progress of the active tasks.
â–ª Problems encountered with the work.
â–ª Problems anticipated with work waiting to be done.
â–ª Technical difficulties being encountered.
When a conflict arises it need not be a negative. Conflict can be positive –
Consider the ideas set out on the following pages.
CONFLICT
Source: Construction Management Induction Program – Module 1 Interpersonal Communicating Skills for
Construction Managers. Extract from Topic Managing Conflict. –Construction Property Services Industry
Skills Council (CPSISC) WELL Program – in Association with BMA Consulting.
Every relationship that we have contains an element of conflict. Conflict can
occur whenever the actions of one person or group frustrate, or are perceived to
frustrate, the actions or goal achievement of another. The main causes of
conflict include:
â–ª Misunderstandings - especially concerning messages, roles,
esponsibilities and tasks.
â–ª Personality clashes.
â–ª Differences in goals.
â–ª Sub-standard performances or quality.
â–ª Differences over methods to be used.
â–ª Problems relating to areas of responsibility.
â–ª Lack of cooperation.
â–ª Problems relating to areas of authority.
â–ª Individual differences.
â–ª Competition for limited resources.
â–ª Non-compliance with rules and policies.
â–ª Competing schedules.
â–ª Pressing deadlines and project management concerns.
Today it is generally thought that it is not so much conflict that
eaks down
effective working relationships, but the destructive nature of some conflict and
the inability to effectively manage it.
Distinguishing between the destructive or constructive nature of conflict is
important. Conflict in itself is healthy and can generate change and creativity.
Conflict can be positive when it:
â–ª Helps to open up discussion of an issue.
â–ª Results in problems being solved.
â–ª Increases the level of individual involvement and interest in an issue.
â–ª Improves communication between people.
â–ª Releases emotions that have been stored up.
â–ª Helps people to develop their abilities.
â–ª Continues to surface without resolution.
Conflict can be negative when it:
â–ª Diverts people from dealing with the really important issues.
â–ª Creates feelings of