A 10-acre pasture site (moderate slope, sandy soil) is to be developed to a high-density single family subdivision. Calculate the range of the estimated increase in runoff due to development for a 1...

1 answer below »

A 10-acre pasture site (moderate slope, sandy soil) is to be developed to a high-density single family subdivision. Calculate the range of the estimated increase in runoff due to development for a 1 inch/hour rainfall. Use a range of values for the pre-development runoff coefficient and a single value for post-development runoff coefficient.

 

Answered 178 days After May 14, 2022

Solution

Banasree answered on Nov 08 2022
50 Votes
Ans. Q = CiA
Estimated run off will be 7%+, pasture, sandy soil, steep = 0.25 min
C value
Area description - Single Family Area = 0.3-0.50
Surface characteristic – Sandy soil, Pasture = 0.10 – 0.25
Run off coefficient
Pasture = 0.12
A = 10 acre = 40468.6 sqm
1 inch/hour = 25.4mm/hr = ...