Great Deal! Get Instant $10 FREE in Account on First Order + 10% Cashback on Every Order Order Now

3. Underground Cavern and 6. Case Studies XXXXXXXXXX/.DS_Store __MACOSX/3. Underground Cavern and 6. Case Studies XXXXXXXXXX/._.DS_Store 3. Underground Cavern and 6. Case Studies XXXXXXXXXX/RSE3010...

1 answer below »
3. Underground Cavern and 6. Case Studies XXXXXXXXXX/.DS_Store
__MACOSX/3. Underground Cavern and 6. Case Studies XXXXXXXXXX/._.DS_Store
3. Underground Cavern and 6. Case Studies XXXXXXXXXX/RSE3010 Assignment 3+6 Final-updated.docx
RSE3010 Mine Geotechnical Engineering
Second Semester 2021
RSE3010 Mine Geotechnical Engineering
Second Semester 2021
Assignment 3 – Empirical Design and Support of Caverns (10 Marks)
Assignment 6 – Case Studies: Design of Snowy XXXXXXXXXXMarks)
Project Information:
The Snowy 2.0 project involves the delivery of a 2000 Megawatt pumped storage scheme in Australia. The project aims to provide increased storage capacity and security for the national electricity network. The proposed scheme will augment the existing 4100 Megawatt Snowy Mountains Hydroelectric Scheme, which is the largest hydropower complex in Australia. Snowy 2.0 combines a high head differential, long and deep waterway tunnels and six 340 MW reversible pump-tu
ines. It will link two existing reservoirs, Tantangara and Talbingo, through 27 km of waterway tunnels and an underground power station. The conceptual design of Snowy 2.0 is shown in Figure 1. Three tunnel boring machines (TBMs) of 11m diameter, two supplied by He
enknecht and one by CREG, are prepared to be delivered to the site and start excavation with drill+blast of the powerhouse caverns once access is achieved, and the photos of 3 TBMs are shown in Figure 2. TBM 1 will excavate the Emergency, Ventilation and Cable Tunnel from the surface in Lobs Hole down to the power station complex. From there, it will tunnel the inclined pressure shaft, linking the headrace tunnel (the upper waterway tunnel) to the large tu
ines within the power station. TBM 2 will excavate the Main Access Tunnel from the surface in Lobs Hole down to the powerstation complex. From there, TBM 2 will be dismantled underground and reassembled at the Talbingo Portal. It will then be shifted on a concrete cradle along the 700m-long Talbingo construction adit before being relaunched underground to excavate the tailrace tunnel. TBM3 will excavate 17km of the headrace tunnel.
Figure 1 Conceptual design of Snowy 2.0 pumped storage project (From Snowyhydro)

Figure 2 Three tunnel boring machines (TBMs) of 11m diameter, two (TBM 1 on Left and TBM 3 on Right) supplied by He
enknecht and one (TBM 2 in the Middle) by CREG (From Snowyhydro)
The main components of the underground powerstation complex are the machine hall, transformer hall and tailrace surge tank. These components are connected via the waterway tunnels, shafts and main access tunnels. The underground powerstation complex is located approximately 750 m below ground. The machine hall will be 30 m wide, 55 m tall and 238 m long. It will house the six pump-tu
ines, motor-generators, main inlet valves and auxiliary balance of plant. The transformer hall will be 21 m wide, 28 m tall, 204 m long and be located downstream of the machine hall. TBM 2 (diameter 11m) will excavate the Main Access Tunnel (the tunnel internal diameter 10m) from the surface in Lobs Hole down to the powerstation complex.
Figure 3 A typical cross-section of the machine hall (Left, 30 m wide and 55 m tall) and transformer hall (right) of Snowy 2.0 (From Chapman et al. 2019)
Geological mapping and borehole investigations are ca
ied out at the project sites. There are two critical geological ground conditions with good quality and poor quality of rock masses, respectively. The estimated rock mass classifications based on RMR, Q-system and GSI are listed in Table 1. The major and intermediate in-situ stresses are 2.3 and 1.5 times the vertical stress, respectively. Mechanical properties of intact sandstone samples from the tests are: σci = 65 MPa, Ei =27 GPa, σt = 9.5 MPa, v= 0.2, γ = 27 kN/m3, c = 4.2 MPa and Φ =34.6°. Two joint sets are observed and can be considered as very unfavourable for the main access tunnel. With a scan line of 285 m, a total of 2569 joints are counted.
Table 1 Estimated rock mass classifications of Snowy 2.0 Projects
        Rock mass quality
        RMR
        Q values
        GSI
        Good
        62
        15
        65
        Poo
        24
        0.5
        25
Questions:
As the geotechnical engineer, you are asked to validate the design and provide the co
esponding supporting systems for the underground powerstation and the main access tunnel (the ove
urden depth can be considered as 750m).
(1) Please estimate the rock mass parameters at the site of the main access tunnel. The below table is recommended to be used to summarise your answer.
Table 1 Rock mass parameters and plastic zone of the main access tunnel
        
        Paramete
        Unit
        GSI=65
        GSI=25
        Hoek-Brown parameters
        m
        
        
        
        
        s
        
        
        
        
        a
        
        
        
        Uniaxial compressive strength
        
        
        
        
        Triaxial compressive strength
        
        
        
        
        Tensile strength
        
        
        
        
        Deformation modulus
        
        
        
        
        Mohr-Coulomb parameters
        c
        
        
        
        
        Î¦
        
        
        
        Kirsch solutions
        Crown and invert
        
        
        
        
        Side walls
        
        
        
        
        Any failure
        
        
        
        Hoek 1998 Analytical solutions
        
        
        
        
        
        
        
        
        
        
        
        
        
        
(2) By using the ‘Decision tree’, Martin’s empirical equation and Kaiser et al’s design chart, identify the dominant modes of failure and potential stress-induced failure depth of the main access tunnel, and compare these results and provide your comments on the failure types. The below tables are recommended to be used to summarise your answer.
Table 2 Quantitative data of Martin’s empirical method
        
        GSI=65
        GSI=25
        
        
        
        
        
        
        
        
        
        
        
        
        Failure level
        
        
Table 3 Quantitative data of the Kaiser et al’s design chart
        
        GSI=65
        GSI=25
        
        
        
        Failure types
        
        
Table 4 Quantitative data of the ‘Decision tree’ method
        
        GSI=65
        GSI=25
        
        
        
        
        
        
        Failure types
        
        
(3) By using RMR based design chart, estimate the maximum and minimum unsupported spans and their co
esponding stand-up times of these two rock masses. What will be the stand-up time for the main access tunnel without support? The below table is recommended to be used to summarise your answer. The use of relevant charts by following the Lecture materials should also be presented to support your results.
Table 5 Quantitative data of the RMR based design chart
        
        RMR=62
        RMR=24
        The minimum unsupported span (m)
        
        
        The maximum stand-up time
        
        
        The maximum unsupported span (m)
        
        
        The minimum stand-up time
        
        
        The main access tunnel span = 11m
        The maximum stand-up time of the tunnel without support
        
        
        Adjusted RMR
        
        
        Support categories
        
        
        Rock bolt sapcing (m)
        
        
        Rock bolt length (m)
        
        
(4) By using the Q-value and Rock Support Chart, design the support for the machine hall, transformer hall and the main access tunnel, respectively. The below table is recommended to be used to summarise your answer. The use of relevant charts by following the Lecture materials should also be presented to support your results.
Table 6 Quantitative data of the Q-value and Rock Support Chart
        
        Machine hall
        Transformer hall
        Main access tunnel
        
        Span
        Wall
        Span
        Wall
        Span
        Wall
        Q values
        
        
        
        
        
        
        
        
        
        
        
        
        ESR
        
        
        
        
        
        
        
        
        
        
        
        
        De (m)
        
        
        
        
        
        
        
        
        
        
        
        
        Support category
        
        
        
        
        
        
        
        
        
        
        
        
        Bolt spacing (m)
        
        
        
        
        
        
        
        
        
        
        
        
        Bolt length (m)
        
        
        
        
        
        
        
        
        
        
        
        
(5) By using the convergence confinement method (CCM) and RocSupport software, calculate the radius of plastic zones and factors of safety of the main access tunnels by selecting these two different solutions (Ca
anza-To
es 2004, Vrakas and Anagnostou 2014) for the shapes of the ground reaction curve (GRC). Please use the (1) Shortcut (reinforcement concrete with σci = 40 MPa, Ei =30 GPa, v= 0.2) to represent the TBM segment, (2) Support installation at the distance from the tunnel face of 3 m, and (3) in terms of Longitudinal Deformation Profile (LDP), select Vlachopoulos and Diederichs, 2009. List a table for the values including the Tunnel Section View and Ground and Support Reaction Curves. The below table is recommended to be used to summarise your answer. The RocSupport charts by flowing the Lecture materials should also be presented to support your results. Apart from the regular word submission, you are required to also submit the saved application file in RocSupport original format (.rsp).
Table 7 Quantitative data of the CCM and RocSupport
        GRC Shape
        Ca
anza-To
es 2004
        Vrakas and Anagnostou 2014
        GSI
        65
        25
        65
        25
        Radius of plastic zone (m)
        
        
        
        
        Radius of plastic zone after support (m)
        
        
        
        
        Tunnel convergence (%)
        
        
        
        
        Tunnel convergence after support (%)
        
        
        
        
        Factor of safety
        
        
        
        
(6) Based on the above empirical and analytical results, please
iefly summarise the potential failure types of the main access tunnel and underground powerstations, respectively, and provide the co
esponding comments on the support methods.
Marking criteria (15 Marks)
        Criteria
        Description
        Marks allocated
        Quantitative calculation and/or qualitative clarification
        Rock mass parameters and plastic zone
        15%
        
        Empirical methods for the main access tunnel
        15%
        
        RMR based Design Chart for the main access tunnel
        15%
        
        Q-value and Rock Support Chart
        15%
        
        RocSupport for the main access tunnel
        10%
        
        Summarise potential failure types and comments
        10%
        Formality and readability
        According to the Marking Ru
ics of Assessment Format outlined in the ‘Report Format Guideline’
        20%
Assignment submission
Please submit the assessment on Moodle. There will be penalty for late submission at a rate of 10% each day that the submission is late. This assignment is due on 26th September, 2021
Page 1
Page 4
__MACOSX/3. Underground Cavern and 6. Case Studies XXXXXXXXXX/._RSE3010 Assignment 3+6 Final-updated.docx
3. Underground Cavern and 6. Case Studies XXXXXXXXXX/RSE3010 Assignment 3+6 Final-updated.pdf
RSE3010 MINE GEOTECHNICAL ENGINEERING
SECOND SEMESTER 2021

Page 1
Assignment 3 – Empirical Design and Support of Caverns (10 Marks)
Assignment 6 – Case Studies: Design of Snowy XXXXXXXXXXMarks)
Project Information:

The Snowy 2.0 project involves the delivery of a 2000 Megawatt pumped storage scheme in Australia. The project
aims to provide increased storage capacity and security for the national electricity network. The proposed scheme
will augment the existing 4100 Megawatt Snowy Mountains Hydroelectric Scheme, which is the largest hydropower
complex in Australia. Snowy 2.0 combines a high head differential, long and deep waterway tunnels and six 340
MW reversible pump-tu
ines. It will link two existing reservoirs, Tantangara and Talbingo, through 27 km of
waterway tunnels and an underground power station. The conceptual design of Snowy 2.0 is shown in Figure 1.
Three tunnel boring machines (TBMs) of 11m diameter, two supplied by He
enknecht and one
Answered 14 days After Sep 10, 2021

Solution

Ishwar answered on Sep 24 2021
137 Votes
Assignment 3–EmpiricalDesign and Support of Caverns (10 Marks)
Assignment 6– Case Studies: Design of Snowy 2.0 (5 Marks)
Student Name
Student ID :
Introduction :
The snowy 2.0 project includes for delivery approximate 200 MW pumped storage scheme in Australia. The project objective is to enhance the storage capacity and security as considering the national electricity network. The existing project will planning for link two existing reservoir i.e. Tantangara and Talbingo using 27 km of waterway tunnel and underground power station. The following figure demonstrate the tunnel design includes three tunnel boring machine of 11m diameter, and preparing to delivered to the site and start excavation using drill and blast of the power house in order to achieve, as shown in following figure.
TBM-1 will excavate for emergency, ventilation and cable tunnel through surface in Lobs hole down to the power station complex. Subsequently, it includes the pressure shaft and engage the headrace tunnel to the large tunnel within the power station. TBM 2 will excavate the primary access tunnel from the surface in lobs hole down to the power station complex. The TBM2 will excavate 17 km of the headrace tunnel. The project report is discuss for the rock classification for snowy 2.0 project includes demonstration of various design aspects such as RMR, Q-value and GSI magnitude as well. That mainly based on the rock mass parameters and plastic zone by considering primary tunnel access. Further, that includes the design parameters as considering Martin’s empirical method, Kaiser et al’s design charts and decision tree’s method as well. Lastly, Q-value and Rock mass parameters calculate for all three segment of tunnels.
Figure 1 Conceptual design of Snowy 2.0 pumped storage project(From Snowyhydro)
Figure 2 Three tunnel boring machines (TBMs) of 11m diameter, two (TBM1 on Left and TBM3 on Right) supplied by He
enknecht and one (TBM2 in the Middle) by CREG (From Snowyhydro)
Mechanical properties of intact sandstone samples from the tests are: σci = 65 MPa, Ei=27 GPa, σt = 9.5 MPa, v= 0.2, γ = 27 kN/m3, c = 4.2 MPa and Φ =34.6°.Two joint sets are observed and can be considered as very unfavourable for the main access tunnel. With a scan line of 285 m, a total of 2569 joints are counted.
Table 1 Estimated rock mass classifications of Snowy 2.0 Projects
    Rock mass quality
    RMR
    Q...
SOLUTION.PDF

Answer To This Question Is Available To Download