2. You are at Disney World and wait 45 minutes to ride the roller coaster at Space Mountain. Guests board the roller coaster in batches of 20. The ride takes 3 minutes and all riders get off at the...

1 answer below »
2. You are at Disney World and wait 45 minutes to ride the roller coaster at Space Mountain. Guests board the roller coaster in batches of 20. The ride takes 3 minutes and all riders get off at the same time. What is the cycle time of this process? What is the throughput time?
Answered 95 days After Jun 01, 2022

Solution

Himanshu answered on Sep 05 2022
71 Votes
Assignment 110016
Answer: The cycle time of a process is the time taken to complete one iteration of the process. In this case, it should be noted that cycle time is the time between two successive rides. Hence, the cycle time of this process is 3 minutes.
Throughput time is the sum of the cycle...