Use the planning budget and actual performance data provided in the Case Study Template to calculate the following variances: Volume Variances for each line item in the Product Margin Statement...

1 answer below »
  1. Use the planning budget and actual performance data provided in the Case Study Template to calculate the following variances:
    1. Volume Variances for each line item in the Product Margin Statement
    2. Flexible Budget Variances for each line item in the Product Margin Statement
    3. Material Quantity Variance for each of the three products, and the Labor Efficiency Variance across all three products.
    4. Material Price Variance for each of the three products, and Labor Rate Variance across all three products.
  2. Using the Cast Study Template, state whether each variance is Favorable or Unfavorable.
  3. Explain which function within the organization (production, purchasing, or human relations) would be the responsible party for the Material Quantity Variances, Labor Efficiency Variance, Material Price Variances, and Labor Rate Variance.
  4. Provide plausible explanations that you could verify with each responsible party relating to the Material Quantity Variances, Labor Efficiency Variance, Material Price Variances, and Labor Rate Variance.
Answered Same Day Jan 27, 2021

Solution

Pallavi answered on Jan 29 2021
154 Votes
Material & Labor Price Va
    Annual Material Quantity and Labor Efficiency Variance
        "As If" Budget                    Actual Costs                    Material Price Variance
        Actual    Planned    "As If"            Actual    Actual    Actual            Actual    Unit    Material
    DIRECT MATERIALS    Quantity    Input    Material            Quantity    Input    Material            Quantity    Price    Price
        Used    Price    Cost            Used    Price    Cost            Used    Variance    Variance
        (in yards)    (per yard)    (Total $)            (in yards)    (per yard)    (Total $)            (in yards)    (per yard)    (Total $)    Fav (Unf)
    Blue Banner Material    11,673    $ 60.00    $ 700,380            11,673    $ 58.80    $ 686,372            11,673    $ 1.20    $ 14,008    Fav
    Multi-color Banner Material    2,550    $ 28.00    $ 71,400            2,550    $ 28.70    $ 73,185            2,550    $ (0.70)    $ (1,785)    (Unf)
    White Banner Material    10,227    $ 40.00    $ 409,080            10,227    $ 40.50    $ 414,194            10,227    $ (0.50)    $ (5,114)    (Unf)
        24450        $ 1,180,860            24450        $ 1,173,751            24450        $ 7,109    Fav
        "As If" Budget                    Actual Costs                    Labor Rate Variance
        Actual    Planned    "As If"            Actual    Actual    Actual            Actual    Wage    Labo
    DIRECT LABOR    Hours    Labor    Labor            Hours    Labor    Labor            Hours    Rate    Rate
        Used    Rate    Cost            Used    Rate    Cost            Used    Variance    Variance
        (in hours)    (per hour)    (Total $)            (in hours)    (per hour)    (Total $)            (in hours)    (per hour)    (Total $)    Fav (Unf)
        6,174.65    $ 40.00    $ 246,986.00            6,174.65    $ 38.00    $ 234,637            6,174.65    $ 2.00    $ 12,349    Fav
        1st Qtr    2nd Qtr    3rd Qtr    4th Qt
    Actual hours used    0.24    0.25    0.23    0.27
    Actual quantity
    Blue Banners - Actual    1018    2725    2880    5050
    Multi-color Banners - Actual    478    980    768    324
    White Banners - Actual    721    1184    2916    5406
    Total qty    2217    4889    6564    10780
    Total hours    532.08    1,222.25    1,509.72    2,910.60    6,174.65
Budgeted Income Statement
        Planning Budget Income Statement
            2020
            1st Qtr    2nd Qtr    3rd Qtr    4th Qt
        Sales Units    2,120    4,760    6,660    10,400
        Sales Revenue    $ 24,620    $ 57,100    $ 80,320    $ 128,100
        Variable Expenses:
        Direct Materials    $ 9,540    $ 21,420    $ 29,970    $ 46,800
        Direct Labor    5,300    11,900    16,650    26,000
        Variable Manufacturing Overhead    795    1,785    2,498    3,900
        Variable S&A    4,770    10,710    14,985    23,400
        Total Variable Expense    $ 20,405    $ 45,815    $ 64,103    $ 100,100
        Contribution margin    $ 4,215    $ 11,285    $ 16,218    $ 28,000
        Fixed Expenses:
        Fixed Manufacturing Overhead    $ 1,000    $ 1,000    $ 1,000    $ 1,000
        Fixed S&A    1,500    1,500    1,500    1,500
        Total Fixed Expenses    $ 2,500    $ 2,500    $ 2,500    $ 2,500
        Operating Income    $ 1,715    $ 8,785    $ 13,718    $ 25,500
Volume Variance Analysis
        Flexible Budget Income Statement                        Planning Budget Income Statement                        Volume Variance Analysis
            2020                        2020                        2020
            1st Qtr    2nd Qtr    3rd Qtr    4th Qtr            1st Qtr    2nd Qtr    3rd Qtr    4th Qtr            1st Qtr    2nd Qtr    3rd Qtr    4th Qtr    Q1 U/F    Q2 U/F    Q3 U/F    Q4 U/F
        Sales Units    2,217    4,889    6,564    10,780        Sales Units    2120    4760    6660    10400        Sales Units    97    129    (96)    380    F    F    U    F
        Sales Revenue    $ 25,826    $ 59,575    $ 77,736    $ 132,078        Sales Revenue    24,620    57,100    80,320    128,100        Sales Revenue    $ 1,206    $ 2,475    $ (2,584)    $ 3,978    F    F    U    F
        Variable Expenses:                        Variable Expenses:                        Variable Expenses:
        Direct Materials    $ 9,977    $ 22,001    $ 29,538    $ 48,510        Direct Materials    $ 9,540    $ 21,420    $ 29,970    $ 46,800        Direct Materials    $ (437)    $ (581)    $ 432    $ (1,710)    U    U    F    U
        Direct Labor    5,543    12,223    16,410    26,950        Direct Labor    5,300    11,900    16,650    26,000        Direct Labor    (243)    (323)    240    (950)    U    U    F    U
        Variable Manufacturing Overhead    3,326    7,334    9,846    16,170        Variable Manufacturing Overhead    3,180    7,140    9,990    15,600        Variable Manufacturing...