Great Deal! Get Instant $10 FREE in Account on First Order + 10% Cashback on Every Order Order Now

The firm manufactures two models of the trans catheter aortic valve replacement system: the system which is equipped with 23 mm valves and the system which is equipped 29 mm valves. The...

1 answer below »

The firm manufactures two models of the trans catheter aortic valve replacement system: the system which is equipped with 23 mm valves and the system which is equipped 29 mm valves.

The expected profit for 23mm system is $300 per unit, while profit for 29mm system is $360 per unit. The firm utilizes aortic valves bought from an external supplier. There is a supply restriction for both of 23 mm and 29mm valves. The current suppler of valves cannot supply more than 300 units of23 mm valvesper week and no more than 600 units of 29 mm valves per week.

The manufacturing time for one23 mm aortic valvesystemis 2 hours per week. The manufacturing time for one29 mm aortic valve system is 2.4 hours per week. There are 1550 hours of total manufacturing time available per week. Determine how many units of 23 mm aortic valve system and 29 mm aortic valve system the firm needs to manufacture per week to maximize profit.

Hint: Set up and solve the problem as Linear or Integer Programming problem using Excel QM, POM, or Solver.

Answered Same Day Dec 27, 2021

Solution

David answered on Dec 27 2021
107 Votes
Discussion question
The firm manufactures two models of the trans catheter aortic valve replacement system: the system which is equipped with 23 mm valves and the system which is equipped 29 mm valves.
The expected profit for 23mm system is $300 per unit, while profit for 29mm system is $360 per unit. The firm utilizes aortic valves bought from an external supplier. There is a supply restriction for both of 23 mm and 29mm valves. The cu
ent suppler of valves cannot supply more than 300 units of23 mm valvesper week and no more than 600 units of 29 mm valves per week.
The manufacturing time for one23 mm aortic valvesystemis 2 hours per week. The manufacturing time for one29 mm aortic valve system is 2.4 hours per week. There are 1550 hours of total manufacturing time available per week. Determine how many units of 23 mm aortic valve system and 29 mm aortic valve system the firm needs to manufacture per week to maximize profit.
Hint: Set up and solve the problem as Linear or Integer Programming problem using Excel QM, POM, or Solver.
Solution:
Given data from the problem:
The two types of the valves are 23 mm valve and 29mm valves
The possible profit from 23 mm valve is $300 per unit.
The possible profit from 29 mm valve is $360 per unit.
Suppose A be the number of valves of 23 mm size and B be the number of valves of 29mm size possible to manufacturer for a week, then the possible profit from the sale of the valves will be,
Objective function:
Z = 300A + 360B ------------- (Maximize)
Constraints:
A
=300
B
=600
Let At be the time of manufacturing the A type of valves per week and the Bt be the time for manufacturing the B type of valves per week.
At = 2 hours/week
Bt = 2.4 hours/week
The total time to manufacture the valves per week,
T= 2A + 2.4B
=1550
Hence the constraints can be put as follows,
Constraints:
A
=300
B
=600
2A + 2.4B
=1550
Objective function:
Objective is to maximize Z = 300A...