Project budget estimate Question Detail: Assume that you have been selected to serve as the project manager for a management consulting project for a client based in the United States. You have...

1 answer below »
Project budget estimate
Question Detail:

Assume that you have been selected to serve as the project manager for a management consulting project for a client based in the United States. You have developed the WBS and listed the activities for the assignment, which involve large-scale market research in a new market. You are responsible for project costs and are keen on developing realistic cost estimates and project budget. You have estimated the following effort:

WBS

Tasks

Duration

Resource Type

Effort in Days

1.1

Final proposal and contract documentation

4 Days

Junior Consultant

4

Legal Consultant

1

Vice President

1

1.2

Assignment kickoff workshop

2 Days

Junior Consultant

2

Senior Consultant

1

Vice President

1

2.1

Designing market research

5 Days

Product Expert

1

Junior Consultant

5

Senior Consultant

2

2.2

Pilot run of market research

10 Days

Junior Consultant

3

Intern

10

Senior Consultant

2

2.3

Final market research design and signoff

2 Days

Junior Consultant

2

Senior Consultant

1

Vice President

1

2.4

Market research 1

32 Days

Junior Consultant

20

Senior Consultant

2

2 Interns*

28

2.5

Market research 2

32 Days

Junior Consultant

20

Senior Consultant

2

2 Interns*

28

2.6

Data collation and analysis

5 Days

Junior Consultant

5

Senior Consultant

3

2 Interns*

5

Vice President

0.5

3.1

Final report preparation

3 Days

Senior Consultant

3

Junior Consultant

3

Vice President

0.5

3.2

Presentation to client

1 Day

Senior Consultant

1

Junior Consultant

1

Vice President

0.5

*Please note the use of 2 resources in this case.
The rates per day for the resources are as follows:

Resource

Rate Per Day

Junior Consultant

$750

Intern

$250

Legal Consultant

$1,500

Product Expert

$3,500

Senior Consultant

$1,500

Vice President

$3,500


The tasks above are listed in sequential order. The exceptions are market research 1 and 2, which can start simultaneously.

This assignment has two parts. Complete Part 2 after completing Part 1.

Part 1:Develop the budget for this project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project. Assume that the payments to all resources are made on a daily basis.

Part 2:For the consulting assignment, assume that the total project budget is spent equally on a daily basis and the work done each day contributes equally toward the project completion. You are now at the end of Day 25 of the project, the company has already spent $48,000, and the project has delivered 5% more than planned at the end of Day 25.

What is your assessment of the schedule performance index (SPI) and cost performance index (CPI) of the project? What actions or corrective actions would you want to take, keeping in mind the project performance so far?

How much more money must be spent to complete the project, and what would be the total cost of the project when it is completed, as per the details given?

Answered Same Day Dec 24, 2021

Solution

David answered on Dec 24 2021
110 Votes
Assume that you have been selected to serve as the project manager for a management consulting
project for a client based in the United States.
You have developed the WBS and listed the activities for the assignment, which involve large-scale
market research in a new market.
You are responsible for project costs and are keen on developing realistic cost estimates and project
udget. You have estimated the following effort:
WBS Tasks Duration Resource Type Effort in
Days
1.1 Final proposal and contract
documentation
4 Days Junior Consultant 4
Legal Consultant 1
Vice President 1
1.2 Assignment kickoff
workshop
2 Days Junior Consultant 2
Senior Consultant 1
Vice President 1
2.1 Designing market research 5 Days Product Expert 1
Junior Consultant 5
Senior Consultant 2
2.2 Pilot run of market research 10 Days Junior Consultant 3
Intern 10
Senior Consultant 2
2.3 Final market research
design and signoff
2 Days Junior Consultant 2
Senior Consultant 1
Vice President 1
2.4 Market research 1 32 Days Junior Consultant 20
Senior Consultant 2
2 Interns* 28
2.5 Market research 2 32 Days Junior Consultant 20
Senior Consultant 2
2 Interns* 28
2.6 Data collation and analysis 5 Days Junior Consultant 5
Senior Consultant 3
2 Interns* 5
Vice President 0.5
3.1 Final report preparation 3 Days Senior Consultant 3
Junior Consultant 3
Vice President 0.5
3.2 Presentation to client 1 Day Senior Consultant 1
Junior Consultant 1
Vice President 0.5
*Please note the use of 2 resources in this case.
The rates per day for the resources are as follows:
Resource
Rate Per
Day
Junior Consultant $750
Intern $250
Legal Consultant $1,500
Product Expert $3,500
Senior Consultant $1,500
Vice President $3,500
The tasks above are listed in sequential order. The exceptions are market...