Materials, labor, and overhead variances—two-variance method Fargo Company manufactures products in batches of 100 units per batch. The company uses a standard cost system and prepares budgets that...

1 answer below »

Materials, labor, and overhead variances—two-variance method

Fargo Company manufactures products in batches of 100 units per batch. The company uses a standard cost system and prepares budgets that call for 500 of these batches per period. Fixed overhead is $60,000 per period. The standard costs per batch follow:

Material (80 gallons)

$32

Labor (60 hours)

480

Factory overhead

252

Standard cost per batch

$764

During the period, 503 batches were manufactured, and the following costs were incurred:

Materials used (40,743 gallons)

$15,482.34

Labor (29,677 hours at $865 per hour)

256,706.05

Actual variable overhead

67,080.00

Actual fixed overhead

60,500.00

Required:

Calculate the variances for materials, labor, and overhead. For overhead, use the two-variance method.

Answered Same Day Dec 24, 2021

Solution

David answered on Dec 24 2021
107 Votes
Material price variance = ( standard rate – actual rate ) actual quantity
=(32*503)- 15482.34 = 16096- 15482.34 = 613.66 favourable.

material usage variance = ( standard quantity – actual quantity ) standard rate
= [(80*503)-40743] 32/80= 201.2 unfavourable.

labour rate variance = =...