Great Deal! Get Instant $10 FREE in Account on First Order + 10% Cashback on Every Order Order Now

ICTNWK529 Install and Manage Complex ICT Networks Trainer’s Guide | V 4.0 | April 2018 | Page 1 of 6 Pass Global Pty Ltd t/a ALTEC College | RTO Code 22034 | CRICOS Code 02926D Approved by: Academic...

1 answer below »
ICTNWK529 Install and Manage Complex ICT Networks
Trainer’s Guide | V 4.0 | April 2018 | Page 1 of 6
Pass Global Pty Ltd t/a ALTEC College | RTO Code 22034 | CRICOS Code 02926D
Approved by: Academic Manager | Next Review: April 2019
6.0 Assessment Tasks

Assessment Task 1:
Assessment Task Analyse Business Requirements
Outcomes Assessed
Performance Criteria:

1.1, 1.2, 1.3

Addresses some elements of performance evidence and
knowledge evidence as shown in the Assessment Matrix
Description:

This is a scenario‐based task that simulates a real‐life business situation. As you will be working in a classroom and
lab environment, you will be provided with a business background/profile to develop the required business context.
For simulation purpose, you will play the role of a Network Analyst working for an IT consulting firm. Your
traine
assessor will play the role of the client where required and provide you with the required information and
feedback.

Your cu
ent institute/college is provided as the case organisation. Use the following information for your reference;

Business Scenario:

ALTEC is a Registered Training Organisation providing a range of vocation and higher education courses to local and
international students. ALTEC’s campus is spanned over two floors of a modern St Kilda Road building, and used by
approximately 800 students and 40 staff members.

ALTEC has two dedicated wired networks for administrative/academic and student services respectively. Print, scan,
email, and internet services are shared across the networks. The college uses its own intranet as a communications
channel, content repository, and an application sharing tool that supports day‐to‐day college activities. The college
uses separate email/data, file and print, database, and legacy servers.

With a view to expand its educational services in higher education, ALTEC has decided to add an additional floor to
its existing campus (ground and first floor). An entire second floor has been leased; and is being fitted out for
academic operations. There are also plans to use a part of the floor as an administrative area. With a view to
segregate its academic operations, ALTEC’s plan for the campus is;

Vocational Course
Ground and First Floor

Higher Education Courses
Second Floor

As the new floor will need to be connected with the existing network, the college has hired services of Bytes
Consultancy to plan and upgrade its existing network. In particular, the college requires that;

1. Two core backbones separating staff and student/visitor access and traffic
2. Different access levels and services across different floors
3. Integrated voice, video, network management, and routing traffic (over VPN)
4. User and department‐based control lists and traffic shaping
ICTNWK529 Install and Manage Complex ICT Networks
Trainer’s Guide | V 4.0 | April 2018 | Page 2 of 6
Pass Global Pty Ltd t/a ALTEC College | RTO Code 22034 | CRICOS Code 02926D
Approved by: Academic Manager | Next Review: April 2019
5. An out–of–band network to access and manage the devices
6. Three distinct connection layers of;
a. Student Administration
. Internet
c. Remote Access
7. Future scalability to an enterprise WAN

You have been given the task to conduct a meeting with the client (traine
assessor role‐play) and confirm the
organisational requirements.

Task

1. Conduct a meeting with the client and confirm specific requirements, including information about the cu
ent
network infrastructure
2. Draw a cu
ent network diagram and identify existing network components
3. Research and develop a solution for the new requirements
4. Draw a proposed physical network topology diagram
5. Draw a proposed logical network topology diagram
6. Briefly explain how the proposed design will meet business requirements

The document should be word‐processed and written as a formal business document with appropriate section
headings and references. Ensure that you maintain effective communication and consultation with the client
(traine
assessor role play).

Word Limit: Maximum four (4) single‐spaced, double‐sided A4 sheets

Assessment Criteria

The following assessment criteria will be used for marking this assessment task. Ensure that you have addressed all
of the criteria in your work;

 Addressed all the requirements of the task
 Maintained effective communication and confirmed client
usiness requirements within the given role play
 Reviewed existing network infrastructure and identified all the key components/devices
 Provided a map of existing network
 The map represents realistic/accurate representation of the cu
ent college network
 Researched and proposed new network hierarchy model to meet the new requirements
 An appropriate network topology design/method is used to show physical and logical network topologies
 Network diagrams are clear, labelled and accurately show logical and physical connections
 Appropriate graphical references/illustrations are used to show various network devices and components
 Network layers are clearly and appropriately shown
 The proposed network design is realistic and supported by external references/models (e.g. CISCO)
 Described how the proposed integrated services will be delivered
 Presented the proposed solution in a coherent and an appropriately structured document
 Compatibility issue with the cu
ent network is evaluated and addressed through product/vendor
information and data

Submission Guidelines

Submit:
 Written planning document
 Network diagrams
 Reference/vendor documents and/or links
Electronic versions of the assessment task and email/electronic submission a
angements are at further discretion
of the traine
assessor.

Note: Keep a copy of all your work/documents as you may need them in the subsequent tasks.
ICTNWK529 Install and Manage Complex ICT Networks
Trainer’s Guide | V 4.0 | April 2018 | Page 3 of 6
Pass Global Pty Ltd t/a ALTEC College | RTO Code 22034 | CRICOS Code 02926D
Approved by: Academic Manager | Next Review: April 2019
Assessment Task 2:

Assessment Task Develop an Implementation Plan
Outcomes Assessed
Performance Criteria:

1.3, 2.1, 2.2, 2.4, 2.5, 6.1

Addresses some elements of performance evidence and
knowledge evidence as shown in the Assessment Matrix
Description:

Continuing in the same role as in the previous assessment task, assume that the solutions proposed by you have
een accepted and you have been asked to develop an implementation plan for installation of the required network
at the college.

An implementation plan lists all the tools
esources required for installation and identifies/outlines key tasks in a
step‐by‐step format within the given time frame.

Using your network plan created in Assessment Task 1, develop an implementation plan for ALTEC for installation of
the new network. Your plan will include;

 Background/Context (why the plan is being prepared)
 Site requirements/assumptions
 Tools and resources required
 Network management tools (network admin and monitoring)
 Implementation tasks
 Security requirements
 Security strategy
 Security tools and methods for ongoing monitoring

The implementation plan should be word‐processed and written as a formal business document with appropriate
section headings and references. Ensure that you maintain effective communication and consultation with the client
(traine
assessor role play).

Word Limit: Maximum four (4) single‐spaced, double‐sided A4 sheets

External sources should be cited using an appropriate referencing system and listed as references at the back of the
document.

Assessment Criteria

The following assessment criteria will be used for marking this assessment task. Ensure that you have addressed all
of the criteria in your work;

 Addressed all the requirements of the task
 Completed the task within the given business context and the required role‐play
 Maintained effective communication and consultation throughout
 Demonstrated the required planning, organisation, and communication skills within the context of this task
 Outlined the business need/case for implementation of new services
 The implementation plan is appropriately structured and covers all the required information
 Network resources are identified and listed
ICTNWK529 Install and Manage Complex ICT Networks
Trainer’s Guide | V 4.0 | April 2018 | Page 4 of 6
Pass Global Pty Ltd t/a ALTEC College | RTO Code 22034 | CRICOS Code 02926D
Approved by: Academic Manager | Next Review: April 2019
 Adequate assumption for pre‐installation site conditions and installation support are made based on the
cu
ent site (college building)
 Implementation tasks are
oken down in key steps from unpacking the equipment to installation and
testing
 Vendor specifications and requirements for installation of various devices are analysed and outlined
 Provided references/guides/links to vendor or other external sources for key tasks
 Network administration tasks and methods are outlined
 Appropriate network management tool/software is recommended for monitoring network performance
 Potential internal and external security threats are identified and described for the college’s network
 Risk mitigation strategies are devised to eliminate/minimise security threats
 Reference documents and links are provided for additional network security information
 Appropriate security tools/software are recommended for continuously monitoring network security
 External sources are acknowledged and cited using a referencing convention

Submission Guidelines

Submit:

 Written Implementation Plan
 Reference/vendor documents and/or links

Electronic versions of the assessment task and email/electronic submission a
angements are at further discretion
of the traine
assessor.

Note: Keep a copy of all your work/documents as you may need them in the subsequent tasks.





























ICTNWK529 Install and Manage Complex ICT Networks
Trainer’s Guide | V 4.0 | April 2018 | Page 5 of 6
Pass Global Pty Ltd t/a ALTEC College | RTO Code 22034 | CRICOS Code 02926D
Approved by: Academic Manager | Next Review: April 2019
Assessment Task 3:

Assessment Task Install, Configure and Test a Complex Network
Outcomes Assessed
Performance Criteria:

2.3, 3.1, 3.2, 3.3, 3.4, 3.5, 3.6, 4.1, 4.2, 4.3, 4.4, 5.1, 5.2, 5.3, 6.2,
6.3, 6.5, 6.6, 6.7, 6.8, 7.1
Answered Same Day Nov 15, 2020 ICTNWK529 Training.Gov.Au

Solution

Amit answered on Nov 16 2020
147 Votes
Full Name :
    
    Student ID :
    
    Subject :
    
    Assignment No :
    
    Due Date :
    
    Lecturer’s Name :
    
ICTNWK529 Install and Manage Complex ICT Networks
Your Name:
Your Email:
College name, University name, Country name
Table of Contents
1.    Task -1    3
2.    Executive summary    3
3.    Scenario of provided business    3
4.    Requirement analysis and proposed solution    4
5.    Cu
ent and proposed physical network    4
6.    Proposed logical design and server implementation    7
7.    Suggested equipments for staff and students    9
8.    Task -2    10
9.    Background    10
10.    Environmental requirements    10
11.    Hardware requirements    10
12.    Resource requirements    11
13.    Security requirements    11
14.    Strategy to implement security policy    11
15.    Methods and tools to monitoring ongoing security    12
16.    Task division and implementation    12
17.    Task -3    15
18.    References:    29
1. Task -1
2. Executive summary
The developed document for ALTEC client organization will help to understand the cu
ent system of ALTEC and also identifies the possible improvements in their projects. The level of client organization named ALTEC will be updated and increases the system values for ALTEC. This will lead to better administration and improved courses for ALTEC. For expanding the position of this potential project some required movements are done here. The involved technologies and developed solution for ALTEC is described with help of diagrams in this document for better understanding. The functionality and network configuration is shown with help of captured screen shots. In this proposed solution, the UTM firewall implementation is also recommended so that the process load on used switches will be reduced and required changes can be implemented in easy and effective manner.
3. Scenario of provided business
The client organization ALTEC is registered place to provide training for higher level courses and other professionals. There are two levels maintained by ALTEC for their 40 staff members and related 800 students. The ALTEC makes use of different print server, file server, database server, and email server for both staff members and related students. For capacity improvements, the addition of extra floor is decided by ALTEC organization. So, the distribution for new campus will be as follows:
1) The ground floor and first floor of building used by ALTEC is reserved for professional courses.
2) The second floor of building used by ALTEC is reserved for higher courses.
4. Requirement analysis and proposed solution
The points showing key requirements for ALTEC organization are listed below:
1) The complete WAN of ALTEC requires improved scalability for added floor.
2) Effective network services for managing network of ALTEC and its devices.
3) Implementation of VPN.
4) Shaping the increased traffic and maintaining control list for added floor.
5) Maintaining access levels for different users.
On bases of above requirements, below listed solution can be developed:
1) Make a meeting with the client ALTEC for improved ability, easy disaster recovery, improved security and all time availability.
2) The separation of IP address for ALTEC staff and related students is developed.
3) The distribution of required switches needs to be done properly.
4) The implemented firewall for complete ALTEC system will maintain effective security and required a
angements of monitoring.
5) For scalability of WAN, the connection zones are maintained in my proposed solution.
6) The used core switches will effectively manage switching, firewall and associated server implementation.
7) The used edge switches will easily maintain the user load.
5. Cu
ent and proposed physical network
The existing network of ALTEC shows the following used components:
1) Cables to connect network,
2) Printers for both users,
3) Servers for both users,
4) WAP,
5) Implementation of required core and edge switches,
6) Routers and firewall.
So, the developed diagram to show the cu
ent physical network of ALTEC organization is shown below:
The developed diagram to show the proposed physical network of ALTEC organization is shown below:
6. Proposed logical design and server implementation
The developed diagram to show the proposed logical network of ALTEC organization is shown below:
The developed diagram to show the proposed server implementation of ALTEC organization is shown below:
7. Suggested equipments for staff and students
The client organization ALTEC is registered place to provide training for higher level courses and other professionals. There are two levels maintained by ALTEC for their 40 staff members and related 800 students. The ALTEC makes use of different print server, file server, database...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here