Complete Problem # 24 in Chapter 8 that focuses on the evaluation of a capital budgetingproject using methods of evaluation. In addition to answering letters A through C, useExcel to calculate the IRR...

1 answer below »

Complete Problem # 24 in Chapter 8 that focuses on the evaluation of a capital budgetingproject using methods of evaluation. In addition to answering letters A through C, useExcel to calculate the IRR for each project and discuss your results. This activity can becompleted using appropriate office software; APA formatting is not required (submit viathe link).24.) NPV vs. Payback Method vs. Profitability Index LOI, 3, 5Alfred Stein is about to invest$1,000. Alfred is a very cautious man and would like to have someexpert advice on which two projects is best for him. He has not told you his exact cost of capitalbecause he likes to keep such information private, but he has told you to consider 8 percent, 10percent, and 12 percent in your calculations. He has also told you that the salesperson fromwhom he expects to purchase his equipment has given him the following expected cost savingspatterns:Year Project 1 Project 2 1 $600 $ XXXXXXXXXX XXXXXXXXXXRequiredA.) Calculate the present value of each project at each of Alfred’s potential costs of capitaland indicate which project is acceptable at each.B.) Calculate the payback period for each project. Does your recommendation to Alfredchange?C.) Calculate the profitability index for each project, using a cost of capital of 10 percent. Which project would you recommend Alfred pursue?

Answered 96 days After May 16, 2022

Solution

Rochak answered on Aug 20 2022
78 Votes
Sheet1
    Investment    $1,000.00
    Cost of Capital    8%    10%    12%
    Cash Flow
    Year    Project 1    Project 2
    0    -$1,000.00    -$1,000.00
    1    $600.00    $300.00
    2    $600.00    $600.00
    3    $600.00    $800.00
    4    $600.00    $700.00
    Answer A:
    Cost of Capital    8%    10%    12%
    NPV - Project 1    $987.28    $901.92    $822.41
    NPV - Project 2    $941.77    $847.76    $760.46
    The project which is acceptable is 'Project 1' at all the cost of...