Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2013 and was completed in 2014. Data relating to the contract are summarized below:
Compute the amount of gross profit or loss to be recognized in 2013 and 2014 using the percentage-of-completion method.
Compute the amount of gross profit or loss to be recognized in 2013 and 2014 using the completed contract method.
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2013 using the percentage-of-completion method.
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2013 using the completed contract method.