Access the Excel file, HW CPM.xlsx . Do all 4 problems in this workbook.

1 answer below »
1
                                                                                a)
                                                                                b)
                                                                                c)
                                                                                d)
        Activity     Activity Time, t (wks)
        A    5                                        C                                H
        B    3                        A
        C    7
        D    6                                        D                F
        E    7            Start                                                                            Finish
        F    3
        G    10
        H    8                        B                E                G
                            e)
        Activity    Start     Activity Time, t (wks)
        A        5
        B        3
        C        7
        D        6
        E        7
        F        3
        G        10
        H        8
Consider the following network and activity times (in weeks).
a) Fill in the nodes with the activity schedule (ES, EF, LS, LF). Identify the critical path.
) How much time will be needed to complete the project?
c) Can activity C be delayed without delaying the entire project? If so, by how many weeks?
d) Can activity D be delayed without delaying the entire project? If so, by how many weeks?
e) Create a Gantt Chart for this project, using a stacked bar chart. The picture of Gantt chart is given in the last tab so you can check yours against it.
2
                                                                b)
                                                                c)
                                                                d)
        Activity    Immd. Pred.     t (wks)                a)
        A    ---    3
        B    ---    1                        A                E
        C    ---    2
        D    A, B, C    4
        E    C, D    5            Start            B                F
        F    A    3
        G    D, F    6
        H    E    4            Finish            C                G
                                        D                H
Mariott Condominium, located near San Diego, California, plans to renovate its main building. The project will begin April 1, and the goal is to complete by August 1 (in 17 weeks). The condominium manager identifed the renovation activities and their estimated time below.
a) Draw a project network. You may want to draw on paper then do it here by connecting the given nodes with arcs (i.e., a
ows). You might not use all of the given arcs.
) What are the critical activities?
c) What activity has the most slack time?
d) Will the project be completed by August 1?
3
                                                                c)
                                                                d)
        Activity    Description    Immd. Pred.     t (wks)                a) & b)
        A    Survey building site    ---    6
        B    Develop initial design    ---    8                        A                E
        C    Obtain board approval    A, B    12
        D    Select architect    C    4
        E    Establish budget    C    6            Start            B                F
        F    Finalize design    D, E    15
        G    Obtain financing    E    12
        H    Hire contractor    F, G    8            Finish            C                G
                                            D                H
        e)
        Activity    Description    Start     Activity Time, t (wks)
        A    Survey building site        6
        B    Develop initial design        8
        C    Obtain board approval        12
        D    Select architect        4
        E    Establish budget        6
        F    Finalize design        15
        G    Obtain financing        12
        H    Hire contractor        8
Rowan College in New Jersey plans to build a new campus center. Below are the activities that need to be completed prior to the construction.
a) Draw a project network.
) Find the activity schedule (ES/EF/LS/LF).
c) What is the critical path?
d) Does it appear feasible that construction of the campus center could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
e) Create a Gantt chart with stacked bar chart. Label the vertical axis with description of the activities (survey building site, etc.). The picture of Gantt chart is given in the last tab so you can check yours against it.
4
                                                                                                c)
        Activity    Immd. Pred.     t (wks)                a) & b)
        A    ---    9
        B    ---    6                        A                E
        C    A    6
        D    A    3
        E    B, C    0            Start            B                F
        F    B, C    3
        G    F    2
        H    D, E    6            Finish            C                G
        I    G, H    3
                                        D                H
                                                        I
Colonial County is planning a new park and recreational area on a recently purchased 250-acre tract. Project development activities include clearing areas for picnic areas, constructing parking lot, building the playground, etc. Below, you are given a list of activities, activity duration (in weeks) and their predecessors.
a) Draw the project network.
) Find the activity schedule (ES/EF/LS/LF). What is the critical path for this network? How many weeks is this project expected to take?
c) The park commissioner would like to open the park to the public within six months from the time the work on the project is started. Does this opening date appear to be feasible? Explain.
1 and 3 Gantt Charts
    Your Gantt charts in #1 and #3 should look like these.
    #1
    #3
Answered Same Day May 26, 2022

Solution

Prince answered on May 27 2022
101 Votes
1
                                                                                a)    A-D-F-H
                                                                                b)    22 weeks
                                                                                c)    Yes, by 2 weeks
                                                                                d)    No.
        Activity     Activity Time, t (wks)
        A    5                                        C    5    12                        H    14    22
        B    3                        A    0    5        7    7    14                        8    14    22
        C    7                        5    0    5
        D    6                                        D    5    11        F    11    14
        E    7            Start                            6    5    11        3    11    14                        Finish
        F    3
        G    10
        H    8                        B    0    3        E    3    10        G    11    21
                                    3    1    4        7    4    11        10    12    22
                            e)
        Activity    Start     Activity Time, t (wks)
        A    0    5
        B    0    3
        C    5    7
        D    5    6
        E    3    7
        F    11    3
        G    11    10
        H    14    8
Consider the following network and activity times (in weeks).
a) Fill in the nodes with the activity schedule (ES, EF, LS, LF). Identify the critical path.
) How much time will be needed to complete the project?
c) Can activity C be delayed without delaying the entire project? If so, by how many weeks?
d) Can activity D be delayed without delaying the entire project? If so, by how many weeks?
e) Create a Gantt Chart for this project, using a stacked bar chart. The picture of Gantt chart is given in the last tab so you can check yours against it.
Gantt Chart
Start    A    B    C    D    E    F    G    H    0    0    5    5    3    11    11    14     Activity Time, t (wks)    
A    B    C    D    E    F    G    H    5    3    7    6    7    3    10    8    Activity
Weeks
2
                                                                b)    A, D, E, H
                                                                c)    F
                                                                d)    Yes
        Activity    Immd. Pred.     t (wks)                a)
        A    ---    3
        B    ---    1                            A    0    3                    F    3    6            G    7    13
        C    ---    2                            3    0    3                    3    7    10            6    10    16
        D    A, B, C    4
        E    C, D    5                Start            B    0    1        D    3    7                                        Finish
        F    A    3                            1    2    3        4    3    7
        G    D,...